4019 S HOOPER AVE 90011
Certificate Information: 4019 S HOOPER AVE 90011
- Application / Permit
- 24014-20000-02684
- Plan Check / Job No.
- B24VN08677
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: Major remodel to existing 1-story single family dwelling with attached garage which includes keeping existing foundation and floor framing and portion of walls existing to remain and reframe roof and walls due to fire damage. Restoration of structure to the same conditions (dimensions, setbacks, area and height) NFPA 13D SPRINKLERED THROUGH OUT
- Permit Issued
- Issued on 12/19/2024
- Issuing Office
- Current Status
- Permit Finaled on 6/28/2025
Permit Application Status History
| Submitted | 6/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/27/2024 | JAD BASMA |
| Corrections Issued | 7/4/2024 | JAD BASMA |
| Quality Review Completed | 7/25/2024 | MICHAEL PEREZ |
| Applicant returned to address corrections | 10/10/2024 | JAD BASMA |
| Applicant returned to address corrections | 10/23/2024 | JAD BASMA |
| Applicant returned to address corrections | 12/4/2024 | JAD BASMA |
| Applicant returned to address corrections | 12/17/2024 | JAD BASMA |
| Plan Check Approved | 12/18/2024 | JAD BASMA |
| Issued | 12/19/2024 | APPLICANT |
| Permit Finaled-Status Void | 6/23/2025 | ALEJANDRO DE ARTOLA |
| Re-Activate Permit | 6/27/2025 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 6/27/2025 | ALEJANDRO DE ARTOLA |
Permit Application Clearance Information
| Address approval | Cleared | 7/8/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/10/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 7/10/2024 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 7/11/2024 | TREVOR QUAN |
| Hydrant and Access approval | Cleared | 8/31/2024 | RUEL COLE |
Contact Information
| Contractor | Aardvark Group Inc The; Lic. No.: 762498-B | , |
| Contractor | The Aardvark Group Inc; Lic. No.: 762498-B | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Wood Frame | 2/3/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 2/5/2025 | Approved | ALEJANDRO DE ARTOLA |
| Wood Frame | 2/5/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2025 | Partial Approval | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 2/24/2025 | Approved | ALEJANDRO DE ARTOLA |
| Sewer | 2/24/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 3/5/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 3/5/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Green Building Rough | 3/5/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 3/5/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 3/11/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 3/11/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 3/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 3/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 3/20/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 3/20/2025 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 3/20/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 3/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 3/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 3/24/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 3/26/2025 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 3/26/2025 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 3/28/2025 | Approved | REGINA MENDEZ |
| ELECTRICAL-Rough | 5/27/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 5/27/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 5/27/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 5/27/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 6/4/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 6/4/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 6/4/2025 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 6/4/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 6/4/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 6/4/2025 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 6/4/2025 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 6/4/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 6/13/2025 | Corrections Issued | WAYNE REGESTER |
| Green Building Final | 6/13/2025 | Corrections Issued | WAYNE REGESTER |
| ELECTRICAL-Final | 6/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 6/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 6/17/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 6/23/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 6/23/2025 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Green Building Final | 6/23/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 6/27/2025 | Permit Finaled | ALEJANDRO DE ARTOLA |
| Service/Power Release | 6/27/2025 | Approved | ALEJANDRO DE ARTOLA |