6227 N SIMPSON AVE 91606
Certificate Information: 6227 N SIMPSON AVE 91606
- Application / Permit
- 24014-20000-02682
- Plan Check / Job No.
- B24VN08665
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: Convert (E) storage into ADU and (N) ADU addition to (E) detached garage . Per CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 8/25/2024
- Issuing Office
- Current Status
- CofO Issued on 6/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/28/2024 | ALFREDO JARA |
| Corrections Issued | 6/30/2024 | ALFREDO JARA |
| Applicant returned to address corrections | 7/13/2024 | ALFREDO JARA |
| Plan Check Approved | 7/29/2024 | ALFREDO JARA |
| Plan Check Approved | 7/31/2024 | ALFREDO JARA |
| Issued | 8/25/2024 | APPLICANT |
| CofO in Progress | 6/6/2025 | RYAN SALAZAR |
| Permit Finaled | 6/6/2025 | RUBEN SALAS |
| CofO Issued | 6/6/2025 | RUBEN SALAS |
| Permit Finaled | 6/6/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/3/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 7/3/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 7/9/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/22/2025 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/22/2025 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 1/27/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 1/29/2025 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2025 | Conditional Approval | JOSE AVILA |
| ELECTRICAL-Rough | 2/24/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 2/24/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 2/24/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Sewer | 2/24/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 2/24/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 2/26/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 2/26/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 3/3/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 3/3/2025 | Partial Approval | MICHAEL CORTEZ |
| Drywall Nailing | 3/6/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 3/7/2025 | Approved | MICHAEL CORTEZ |
| Final | 4/17/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 4/17/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 4/17/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 4/17/2025 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 4/17/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 5/1/2025 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 5/1/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 6/5/2025 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 6/5/2025 | Approved | RYAN SALAZAR |