11104-11106 W OXNARD ST 91601

Certificate Information: 11104-11106 W OXNARD ST 91601

Application / Permit
24014-20000-02641
Plan Check / Job No.
B24VN08563
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: 412 SF ADDITION TO EXISTING SFD
Permit Issued
Issued on 8/16/2024
Issuing Office
Current Status
CofO Issued on 2/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/20/2024 APPLICANT
Assigned to Plan Check Engineer 6/26/2024 ZAW HAN
Corrections Issued 6/27/2024 ZAW HAN
Applicant returned to address corrections 8/14/2024 AUNG SOE
Plan Check Approved 8/15/2024 AUNG SOE
Issued 8/16/2024 APPLICANT
CofO in Progress 9/30/2025 JOSE AVILA
No Progress 1/23/2026 JOSE AVILA
CofO in Progress 1/23/2026 JOSE AVILA
Permit Finaled 2/12/2026 RUBEN SALAS
CofO Issued 2/12/2026 RUBEN SALAS
Permit Finaled 2/12/2026 RUBEN SALAS

Permit Application Clearance Information

CPC Cleared 7/30/2024 NATHAN ROMINE
Highway dedication Cleared 8/2/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 8/2/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 8/5/2024 BIAINA HARITUNIAN
Sewer availability Cleared 8/5/2024 BIAINA HARITUNIAN
ZA Case Cleared 8/7/2024 NATHAN ROMINE

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/23/2024 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 9/30/2024 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 10/2/2024 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 10/3/2024 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 10/21/2024 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 10/24/2024 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 11/14/2024 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 12/2/2024 Approved JACK KARGODORIAN
HVAC-Rough 12/2/2024 Approved JACK KARGODORIAN
PLUMBING-Rough 12/2/2024 Approved JACK KARGODORIAN
Wood Frame 12/2/2024 Corrections Issued JACK KARGODORIAN
BUILDING-Rough-Frame 12/26/2024 Corrections Issued JOSE AVILA
Deputy Wood Construction 12/31/2024 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 1/7/2025 Approved JOSE AVILA
Drywall Nailing 1/31/2025 Approved MISAEL ESPARZA
Interior/Exterior Lathing 1/31/2025 Partial Approval MISAEL ESPARZA
Shower Pan 1/31/2025 Approved MISAEL ESPARZA
Final 9/10/2025 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 9/10/2025 Approved JOSE AVILA
Green Building Final 9/10/2025 Approved JOSE AVILA
Green Building Rough 9/10/2025 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 9/10/2025 SGSOV Not Ready JOSE AVILA
Smoke Detectors 9/10/2025 Approved JOSE AVILA
Final 9/15/2025 No Access for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 9/15/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Final 9/29/2025 OK to Issue CofO JOSE AVILA
SGSOV-Seismic Gas S/O Valve 9/29/2025 SGSOV Approved JOSE AVILA