9010 N VARNA AVE 91331

Certificate Information: 9010 N VARNA AVE 91331

Application / Permit
24014-20000-02618
Plan Check / Job No.
B24VN08497
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD TO AND CONVERT (E) DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d).
Permit Issued
Issued on 2/28/2025
Issuing Office
Valley
Current Status
Issued on 2/28/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/14/2024 APPLICANT
Assigned to Plan Check Engineer 6/21/2024 HAYATO TSUCHIYA
Corrections Issued 6/22/2024 HAYATO TSUCHIYA
Building Plans Picked Up 7/29/2024 APPLICANT
Applicant returned to address corrections 1/28/2025 ANGELICA DAVE
Plan Check Approved 2/25/2025 YAQUB MIRZA
Issued 2/28/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/6/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 8/6/2024 BIAINA HARITUNIAN
Sewer availability Cleared 8/9/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 9/27/2024 MICHELLE RIOS
Construction near power lines Cleared 11/13/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/26/2025 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 6/27/2025 Approved VINCENT HANLEY
Footing/Foundation/Slab 6/27/2025 Approved VINCENT HANLEY
PLUMBING-Rough 6/27/2025 Partial Approval VINCENT HANLEY
Pre-Inspection 7/17/2025 Approved NICHOLAS TROWBRIDGE
Wood Frame 7/17/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 7/29/2025 Partial Approval VINCENT HANLEY
PLUMBING-Final 7/29/2025 Corrections Issued VINCENT HANLEY
Pre-Inspection 7/29/2025 Approved VINCENT HANLEY
Wood Frame 8/7/2025 Approved JACK KARGODORIAN
PLUMBING-Rough 10/30/2025 Not Ready for Inspection WAYNE REGESTER
Wood Frame 10/30/2025 Not Ready for Inspection WAYNE REGESTER
Sewer 11/6/2025 Approved VINCENT HANLEY
Underground Mechanical 11/6/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 1/21/2026 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 2/4/2026 Approved VINCENT HANLEY
Green Building Rough 2/4/2026 Not Ready for Inspection VINCENT HANLEY
Interior/Exterior Lathing 2/4/2026 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 2/25/2026 Corrections Issued VINCENT HANLEY
ELECTRICAL-Rough 2/25/2026 Corrections Issued VINCENT HANLEY
HVAC-Rough 2/25/2026 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 2/25/2026 Approved VINCENT HANLEY
ELECTRICAL-Rough 2/27/2026 Approved VINCENT HANLEY
Gas Test 2/27/2026 Approved VINCENT HANLEY
PLUMBING-Rough 2/27/2026 Approved VINCENT HANLEY
Insulation 3/3/2026 No Access for Inspection OGANES TARAKHCHYAN
Insulation 3/4/2026 Approved MICHEL ABAJAN
Shower Pan 3/4/2026 Approved MICHEL ABAJAN
Drywall Nailing 3/6/2026 Approved OGANES TARAKHCHYAN
Green Building Rough 3/6/2026 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 3/10/2026 Not Ready for Inspection OGANES TARAKHCHYAN
Final 4/15/2026 No Access for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 4/15/2026 SGSOV Not Ready OGANES TARAKHCHYAN
BUILDING-Rough-Frame 4/17/2026 Approved OGANES TARAKHCHYAN
Final 4/17/2026 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 4/17/2026 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 4/17/2026 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 4/17/2026 Approved OGANES TARAKHCHYAN