13182-13184 W BRACKEN ST 91331
Certificate Information: 13182-13184 W BRACKEN ST 91331
- Application / Permit
- 24014-20000-02617
- Plan Check / Job No.
- B24VN08496
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDTION AND GARAGE CONVERSION TO CREATE AN ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e)
- Permit Issued
- Issued on 9/9/2024
- Issuing Office
- Current Status
- CofO Issued on 6/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/21/2024 | NGHI SU |
| Corrections Issued | 6/22/2024 | NGHI SU |
| Applicant returned to address corrections | 8/21/2024 | NGHI SU |
| Applicant returned to address corrections | 8/29/2024 | NGHI SU |
| Plan Check Approved | 9/5/2024 | CARLOS MONTES |
| Issued | 9/9/2024 | APPLICANT |
| CofO in Progress | 6/12/2025 | MICHEL ABAJAN |
| Permit Finaled | 6/20/2025 | RUBEN SALAS |
| CofO Issued | 6/20/2025 | RUBEN SALAS |
| Permit Finaled | 6/20/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/8/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 7/8/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/9/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hoerner,, John Brent; Lic. No.: S2145 | 24024 VIA CANDELA VALENCIA, CA 91355 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/8/2025 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Rough | 1/10/2025 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 1/10/2025 | Partial Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 1/13/2025 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2025 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 1/27/2025 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 1/27/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 1/27/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 1/29/2025 | Approved | MICHEL ABAJAN |
| Green Building Rough | 1/29/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 1/29/2025 | Approved | MICHEL ABAJAN |
| Shower Pan | 1/29/2025 | Approved | MICHEL ABAJAN |
| Insulation | 1/31/2025 | Corrections Issued | LOUIS ESCOTO |
| Insulation | 2/3/2025 | Conditional Approval | MICHEL ABAJAN |
| Drywall Nailing | 2/4/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Interior/Exterior Lathing | 2/4/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 5/6/2025 | Approved | MICHEL ABAJAN |
| Final | 5/6/2025 | Corrections Issued | MICHEL ABAJAN |
| PLUMBING-Final | 5/6/2025 | Approved | MICHEL ABAJAN |
| Final | 6/3/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 6/3/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 6/3/2025 | SGSOV Not Ready | KEVIN BERBERYAN |
| Smoke Detectors | 6/3/2025 | Approved | KEVIN BERBERYAN |
| Final | 6/11/2025 | OK to Issue CofO | MICHEL ABAJAN |
| Green Building Final | 6/11/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 6/11/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 6/11/2025 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 6/11/2025 | Approved | MICHEL ABAJAN |