9758 N COMANCHE AVE 91311

Certificate Information: 9758 N COMANCHE AVE 91311

Application / Permit
24014-20000-02611
Plan Check / Job No.
B24VN08473
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* GROUND FLOOR ADDITION TO (E) DETACHED 2-CAR GARAGE AND SECOND STORY ADU ADDITION PER LAMC 12.22A.33(c)-(d).
Permit Issued
Issued on 9/6/2024
Issuing Office
Current Status
CofO Issued on 1/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2024 APPLICANT
Assigned to Plan Check Engineer 6/19/2024 VIVIAN LAO
Corrections Issued 6/28/2024 VIVIAN LAO
Quality Review Completed 7/5/2024 GARO TELMI
Plan Check Approved 9/6/2024 VIVIAN LAO
Issued 9/6/2024 APPLICANT
CofO in Progress 1/16/2025 DAVID SCANTLIN
Permit Finaled 1/17/2025 JOHN JANSON
CofO Issued 1/17/2025 JOHN JANSON
Permit Finaled 1/17/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/5/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/5/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 7/5/2024 CARLOS AGUILERA
Sewer availability Cleared 7/5/2024 CARLOS AGUILERA
Construction within easement Cleared 8/23/2024 RIDWAN HARDY

Contact Information

Contractor S L G General Construction; Lic. No.: 1088732-B       ,
Engineer Rhee,, Kyle; Lic. No.: NA78215       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/12/2024 Approved DAVID SCANTLIN
Special/Order Compliance 9/12/2024 Approved HENRY KIM
Sewer 9/18/2024 Approved DAVID SCANTLIN
Gas Test 9/23/2024 Approved DAVID SCANTLIN
PLUMBING-Rough 9/23/2024 Partial Approval DAVID SCANTLIN
Underground Mechanical 9/23/2024 Approved DAVID SCANTLIN
Footing/Foundation/Slab 9/30/2024 Corrections Issued DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 10/21/2024 Partial Approval DAVID SCANTLIN
BUILDING-Rough-Frame 11/12/2024 Corrections Issued DAVID SCANTLIN
ELECTRICAL-Rough 11/12/2024 Approved DAVID SCANTLIN
Green Building Rough 11/12/2024 Not Ready for Inspection DAVID SCANTLIN
HVAC-Rough 11/12/2024 Approved DAVID SCANTLIN
PLUMBING-Rough 11/12/2024 Approved DAVID SCANTLIN
Underground Mechanical 11/12/2024 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 11/21/2024 Corrections Issued DAVID SCANTLIN
Green Building Rough 11/21/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 11/21/2024 Partial Approval DAVID SCANTLIN
Shower Pan 11/21/2024 Approved DAVID SCANTLIN
Insulation 11/26/2024 Approved DAVID SCANTLIN
Drywall Nailing 11/27/2024 Approved DAVID SCANTLIN
Insulation 11/27/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 12/9/2024 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 1/15/2025 Approved DAVID SCANTLIN
Final 1/15/2025 OK to Issue CofO DAVID SCANTLIN
Footing/Foundation/Slab 1/15/2025 Approved DAVID SCANTLIN
Green Building Final 1/15/2025 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 1/15/2025 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 1/15/2025 Approved DAVID SCANTLIN