- Permit Issued
- Issued on 7/8/2024
- Issuing Office
- Current Status
- CofO Issued on 2/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/20/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 6/22/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 6/24/2024 | APPLICANT |
| Plan Check Approved | 7/8/2024 | GIOVANNY CHAVEZ |
| Issued | 7/8/2024 | APPLICANT |
| CofO in Progress | 1/21/2025 | OGANES TARAKHCHYAN |
| Permit Finaled | 2/4/2025 | RUBEN SALAS |
| CofO Issued | 2/4/2025 | RUBEN SALAS |
| Permit Finaled | 2/4/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/24/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2024 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 6/24/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/24/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 6/24/2024 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/23/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 7/23/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 7/23/2024 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/21/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Green Building Rough | 8/21/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| PLUMBING-Rough | 8/21/2024 | Partial Approval | SALVADOR MARTINEZ |
| Insulation | 8/23/2024 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 9/12/2024 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 9/12/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Rough | 9/12/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Insulation | 9/12/2024 | Partial Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 9/12/2024 | Approved | OGANES TARAKHCHYAN |
| Sewer | 9/12/2024 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 9/12/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Rough | 9/17/2024 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 9/17/2024 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 9/19/2024 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 9/23/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 9/23/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 9/23/2024 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 9/27/2024 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 9/27/2024 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 12/20/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 12/20/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 12/20/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 12/20/2024 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 12/20/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 1/16/2025 | OK to Issue CofO | OGANES TARAKHCHYAN |