20112 W HALSTED ST 91311
Certificate Information: 20112 W HALSTED ST 91311
- Application / Permit
- 24014-20000-02605
- Plan Check / Job No.
- B24VN08462
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 15'-0" x 13'-6" REAR ADDITION TO THE (E) SINGLE FAMILY DWELLING AND 19'-8" x 36'-5" REAR PATIO COVER ADDITION.
- Permit Issued
- Issued on 8/19/2024
- Issuing Office
- Current Status
- CofO Corrected on 2/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/21/2024 | GIOVANNY CHAVEZ |
| Corrections Issued | 6/25/2024 | GIOVANNY CHAVEZ |
| Plan Check Approved | 7/11/2024 | GIOVANNY CHAVEZ |
| Issued | 8/19/2024 | APPLICANT |
| CofO in Progress | 12/31/2024 | DAVID SCANTLIN |
| Re-Activate Permit | 2/13/2025 | JOHN JANSON |
| CofO Issued-Status Void | 2/13/2025 | JOHN JANSON |
| Permit Finaled-Status Void | 2/13/2025 | JOHN JANSON |
| Permit Finaled | 2/13/2025 | JOHN JANSON |
| CofO Corrected | 2/13/2025 | JOHN JANSON |
| Permit Finaled | 2/13/2025 | JOHN JANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/25/2024 | EDGAR PASCUA |
| Roof/Waste drainage to street | Cleared | 6/29/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/29/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/2/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Caribou Builder Group Inc; Lic. No.: 1108665-B | , |
| Engineer | Park,, Juntae; Lic. No.: NA65104 | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 8/21/2024 | Corrections Issued | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 8/21/2024 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2024 | Partial Approval | DAVID SCANTLIN |
| Rough-Elec/Plmb/HVAC | 9/3/2024 | Approved | DAVID SCANTLIN |
| Wood Frame | 9/3/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 9/11/2024 | Corrections Issued | DAVID SCANTLIN |
| Drywall Nailing | 9/23/2024 | Approved | DAVID SCANTLIN |
| Green Building Rough | 9/23/2024 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 10/11/2024 | Approved | DAVID SCANTLIN |
| Wood Frame | 10/11/2024 | Approved | DAVID SCANTLIN |
| Final | 12/30/2024 | OK to Issue CofO | DAVID SCANTLIN |
| Footing/Foundation/Slab | 12/30/2024 | Approved | DAVID SCANTLIN |
| Green Building Final | 12/30/2024 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 12/30/2024 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 12/30/2024 | Approved | DAVID SCANTLIN |