11048 N MEMORY PARK AVE 91345
Certificate Information: 11048 N MEMORY PARK AVE 91345
- Application / Permit
- 24014-20000-02595
- Plan Check / Job No.
- B24VN08440
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: New 1-story addition to an existing 2-story S.F.D.
- Permit Issued
- Issued on 9/11/2024
- Issuing Office
- Current Status
- CofO Issued on 7/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/18/2024 | CAROLEAN BASMA |
| Corrections Issued | 6/19/2024 | CAROLEAN BASMA |
| Applicant returned to address corrections | 8/20/2024 | CAROLEAN BASMA |
| Plan Check Approved | 8/22/2024 | CAROLEAN BASMA |
| Issued | 9/11/2024 | APPLICANT |
| CofO in Progress | 7/7/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 7/22/2025 | RUBEN SALAS |
| Permit Finaled | 7/22/2025 | RUBEN SALAS |
| CofO Issued | 7/22/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/25/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/26/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/16/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/9/2024 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 10/10/2024 | Conditional Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 10/10/2024 | Conditional Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Wood Frame | 10/18/2024 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2024 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/21/2024 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2024 | Partial Approval | JENNIFER RABUCHIN |
| Special/Order Compliance | 11/1/2024 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/12/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 11/12/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Rough-Elec/Plmb/HVAC | 11/12/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Deputy Wood Construction | 11/13/2024 | Conditional Approval | ROBERT GOLD |
| Insulation | 11/25/2024 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 11/25/2024 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 11/25/2024 | Corrections Issued | MISAEL ESPARZA |
| Shower Pan | 11/25/2024 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 12/2/2024 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 12/2/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 12/2/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 12/2/2024 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/13/2024 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 12/13/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 12/13/2024 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 12/13/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 12/13/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/13/2024 | Approved | JENNIFER RABUCHIN |
| Final | 6/18/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 6/18/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 6/18/2025 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 6/18/2025 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 6/18/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 7/7/2025 | Approved | JENNIFER RABUCHIN |
| Final | 7/7/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 7/7/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 7/7/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 7/7/2025 | Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 7/7/2025 | Approved | JENNIFER RABUCHIN |