5815 W 77TH PL 90045
Certificate Information: 5815 W 77TH PL 90045
- Application / Permit
- 24014-20000-02589
- Plan Check / Job No.
- B24VN08412
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED ADDITION AND MAJOR REMODEL TO (E) SFD. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 8/8/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/20/2024 | RAPHAEL ROSAS |
| Corrections Issued | 6/28/2024 | RAPHAEL ROSAS |
| Quality Review Completed | 6/28/2024 | STEVEN KIM |
| Building Plans Picked Up | 7/1/2024 | APPLICANT |
| Applicant returned to address corrections | 8/7/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 8/8/2024 | RAPHAEL ROSAS |
| Issued | 8/8/2024 | APPLICANT |
| CofO in Progress | 5/13/2025 | JESUS PINEDA |
| Permit Finaled | 5/16/2025 | RICHARD STEINBACH |
| CofO Issued | 5/16/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/16/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/5/2024 | VASIL MIHALEV |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2024 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 7/6/2024 | DARIN LAM |
| Sewer availability | Cleared | 7/6/2024 | DARIN LAM |
| Specific Plan | Cleared | 7/23/2024 | HAMID GHAEMMAGHAMI |
| GPI Written Notices | Cleared | 8/7/2024 | RAPHAEL ROSAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rodriguez,, Jacob; Lic. No.: S5084 | 8206 ENCINO AVE NORTHRIDGE, CA 91325 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/26/2024 | Corrections Issued | BOBBY KEY |
| Special/Order Compliance | 9/26/2024 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 9/27/2024 | Approved | MICHAEL ALLEN |
| Deputy Drilled-In Anchors | 10/10/2024 | Conditional Approval | BOBBY KEY |
| Deputy Wood Construction | 10/10/2024 | Conditional Approval | BOBBY KEY |
| Wood Frame | 10/18/2024 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2024 | Not Ready for Inspection | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Special/Order Compliance | 11/19/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 12/3/2024 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Rough | 12/3/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Rough | 12/3/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 12/4/2024 | Approved | BOBBY KEY |
| HVAC-Rough | 12/4/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 12/4/2024 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 12/9/2024 | Partial Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 12/9/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 12/11/2024 | Not Ready for Inspection | HERBERT GIRON |
| Green Building Rough | 12/11/2024 | Not Ready for Inspection | HERBERT GIRON |
| Verify Sprinkler Sign Off | 12/11/2024 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 12/16/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 12/16/2024 | Approved | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 12/16/2024 | Approved | TEMISTOCLES CAAL |
| Insulation | 12/23/2024 | Approved | EVAN COOPER |
| Drywall Nailing | 12/30/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 1/2/2025 | Approved | TEMISTOCLES CAAL |
| Service/Power Release | 2/24/2025 | Not Ready for Inspection | HERBERT GIRON |
| Special/Order Compliance | 2/24/2025 | Partial Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 3/14/2025 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Final | 3/18/2025 | Not Ready for Inspection | JESUS PINEDA |
| Service/Power Release | 3/18/2025 | Not Ready for Inspection | JESUS PINEDA |
| ELECTRICAL-Final | 4/10/2025 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Final | 4/10/2025 | Not Ready for Inspection | JESUS PINEDA |
| ELECTRICAL-Final | 4/11/2025 | Approved | JESUS PINEDA |
| Service/Power Release | 4/11/2025 | Approved | JESUS PINEDA |
| HVAC-Final | 4/23/2025 | Corrections Issued | JESUS PINEDA |
| Final | 4/25/2025 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 4/25/2025 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Final | 4/25/2025 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 4/25/2025 | SGSOV Not Ready | JESUS PINEDA |
| Smoke Detectors | 4/25/2025 | Approved | JESUS PINEDA |
| Gas Test | 4/30/2025 | Approved | TEMISTOCLES CAAL |
| Green Building Final | 4/30/2025 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 4/30/2025 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 4/30/2025 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 4/30/2025 | SGSOV Approved | TEMISTOCLES CAAL |
| Final | 5/13/2025 | OK to Issue CofO | JESUS PINEDA |