23530 W CLARENDON ST 91367

Certificate Information: 23530 W CLARENDON ST 91367

Application / Permit
24014-20000-02582
Plan Check / Job No.
B24VN08396
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan. Rear additions and remodel of existing single family dwelling with attached garage. Work per engineer design.
Permit Issued
Issued on 8/7/2024
Issuing Office
Current Status
CofO Issued on 7/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/13/2024 APPLICANT
Assigned to Plan Check Engineer 6/18/2024 ADAM HEGAZI
Corrections Issued 6/20/2024 ADAM HEGAZI
Plan Check Approved 7/3/2024 ZAW HAN
Issued 8/7/2024 APPLICANT
CofO in Progress 6/26/2025 GEVORK IPCHYAN
CofO Issued 7/24/2025 DANIEL ORRANTE
Permit Finaled 7/24/2025 DANIEL ORRANTE

Permit Application Clearance Information

GPI Written Notices Cleared 6/20/2024 ADAM HEGAZI
Grading Pre-Inspection Cleared 6/20/2024 ADAM HEGAZI
Roof/Waste drainage to street Cleared 6/29/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/1/2024 CARLOS AGUILERA
Sewer availability Cleared 7/1/2024 CARLOS AGUILERA

Contact Information

Contractor Warren Development Llc; Lic. No.: 1098736-B       ,
Engineer Medina,, Armando; Lic. No.: C83911 2000 W LINCOLN AVE      MONTEBELLO, CA 90640

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/8/2024 Not Ready for Inspection GEVORK IPCHYAN
PLUMBING-Rough 8/9/2024 Partial Approval GEVORK IPCHYAN
Deputy Drilled-In Anchors 8/12/2024 Partial Approval TROY SANDERS
Excavation/Setback/Form/Re-Bar 8/13/2024 Not Ready for Inspection GEVORK IPCHYAN
Footing/Foundation/Slab 8/19/2024 Approved GEVORK IPCHYAN
Deputy Reinf. Concrete 8/22/2024 Conditional Approval TROY SANDERS
BUILDING-Rough-Frame 9/25/2024 Partial Approval GEVORK IPCHYAN
ELECTRICAL-Rough 9/25/2024 Approved GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 9/25/2024 Partial Approval GEVORK IPCHYAN
Green Building Rough 9/25/2024 Not Ready for Inspection GEVORK IPCHYAN
HVAC-Rough 9/25/2024 Approved GEVORK IPCHYAN
PLUMBING-Rough 9/25/2024 Approved GEVORK IPCHYAN
Rough-Elec/Plmb/HVAC 9/25/2024 Approved GEVORK IPCHYAN
Deputy Wood Construction 9/26/2024 Conditional Approval TROY SANDERS
Insulation 10/7/2024 Approved TROY SANDERS
Interior/Exterior Lathing 10/7/2024 Partial Approval TROY SANDERS
Shower Pan 10/7/2024 Approved TROY SANDERS
Interior/Exterior Lathing 10/9/2024 Partial Approval TROY SANDERS
Drywall Nailing 10/18/2024 Approved ARUTYUN MADATYAN
Special/Order Compliance 1/30/2025 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 6/11/2025 Approved GEVORK IPCHYAN
Final 6/11/2025 Not Ready for Inspection GEVORK IPCHYAN
Green Building Final 6/11/2025 Approved GEVORK IPCHYAN
Green Building Rough 6/11/2025 Approved GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 6/11/2025 SGSOV Not Ready GEVORK IPCHYAN
Smoke Detectors 6/11/2025 Not Ready for Inspection GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 6/16/2025 SGSOV Not Ready GEVORK IPCHYAN
ELECTRICAL-Final 6/25/2025 Approved GEVORK IPCHYAN
Final 6/25/2025 OK to Issue CofO GEVORK IPCHYAN
HVAC-Final 6/25/2025 Approved GEVORK IPCHYAN
PLUMBING-Final 6/25/2025 Approved GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 6/25/2025 SGSOV Approved GEVORK IPCHYAN
Smoke Detectors 6/25/2025 Approved GEVORK IPCHYAN