423-423 1/2 E 25TH ST 90011
Certificate Information: 423-423 1/2 E 25TH ST 90011
- Application / Permit
- 24014-20000-02576
- Plan Check / Job No.
- B24VN08385
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 10'-0" X 10'-11" ADDITION TO & REMODEL (E) SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 1/6/2025
- Issuing Office
- Metro
- Current Status
- CofO in Progress on 9/8/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/20/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 6/22/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 6/24/2024 | APPLICANT |
| Plan Check Approved | 7/25/2024 | DANIEL ABRAMYAN |
| Issued | 1/6/2025 | APPLICANT |
| CofO in Progress | 9/8/2025 | DANIEL GUEVARA |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2024 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 7/25/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 7/25/2024 | DAVID LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEREMY TODD, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARVIN FONSECA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GUEVARA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/13/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 1/13/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| METHANE-Barrier | 1/13/2025 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| METHANE-Subgrade | 1/13/2025 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 1/14/2025 | Corrections Issued | DANIEL GUEVARA |
| METHANE-Barrier | 1/14/2025 | Not Ready for Inspection | DANIEL GUEVARA |
| METHANE-Subgrade | 1/14/2025 | Not Ready for Inspection | DANIEL GUEVARA |
| Deputy Drilled-In Anchors | 2/4/2025 | Approved | DANIEL GUEVARA |
| ELECTRICAL-Rough | 4/15/2025 | Approved | DANIEL GUEVARA |
| HVAC-Rough | 4/15/2025 | Approved | DANIEL GUEVARA |
| Insulation | 4/15/2025 | Approved | DANIEL GUEVARA |
| PLUMBING-Rough | 4/15/2025 | Approved | DANIEL GUEVARA |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2025 | Approved | DANIEL GUEVARA |
| Footing/Foundation/Slab | 5/20/2025 | Approved | DANIEL GUEVARA |
| Interior/Exterior Lathing | 5/20/2025 | Approved | DANIEL GUEVARA |
| METHANE-Barrier | 5/20/2025 | Approved | DANIEL GUEVARA |
| METHANE-Subgrade | 5/20/2025 | Approved | DANIEL GUEVARA |
| Wood Frame | 5/20/2025 | Approved | DANIEL GUEVARA |
| Drywall Nailing | 5/30/2025 | Approved | DANIEL GUEVARA |
| Green Building Rough | 5/30/2025 | Approved | DANIEL GUEVARA |
| BUILDING-Rough-Frame | 7/1/2025 | Approved | DANIEL GUEVARA |
| ELECTRICAL-Final | 7/1/2025 | Approved | DANIEL GUEVARA |
| Final | 7/1/2025 | Not Ready for Inspection | DANIEL GUEVARA |
| Green Building Final | 7/1/2025 | Approved | DANIEL GUEVARA |
| METHANE-Final | 7/1/2025 | Approved | DANIEL GUEVARA |
| METHANE-Rough | 7/1/2025 | Approved | DANIEL GUEVARA |
| SGSOV-Seismic Gas S/O Valve | 7/1/2025 | SGSOV Not Ready | DANIEL GUEVARA |
| Smoke Detectors | 7/1/2025 | Corrections Issued | DANIEL GUEVARA |
| PLUMBING-Final | 7/8/2025 | Approved | DANIEL GUEVARA |
| Special/Order Compliance | 7/10/2025 | Corrections Issued | DANIEL GONZALEZ |
| Final | 7/23/2025 | Not Ready for Inspection | DANIEL GUEVARA |
| HVAC-Final | 7/23/2025 | Approved | DANIEL GUEVARA |
| SGSOV-Seismic Gas S/O Valve | 7/23/2025 | SGSOV Approved | DANIEL GUEVARA |
| Smoke Detectors | 7/23/2025 | Approved | DANIEL GUEVARA |
| Final | 8/18/2025 | Conditional Approval | DANIEL GUEVARA |
| Gas Test | 8/22/2025 | Approved | DANIEL GUEVARA |
| SGSOV-Seismic Gas S/O Valve | 8/22/2025 | SGSOV Approved | DANIEL GUEVARA |
| Final | 9/3/2025 | OK to Issue CofO | DANIEL GUEVARA |