10403 N COLLETT AVE 91344
Certificate Information: 10403 N COLLETT AVE 91344
- Application / Permit
- 24014-20000-02547
- Plan Check / Job No.
- B24VN08310
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- TO REMOVE ALUMINUM PATIO COVER AND REAR ADDITION TO THE (E) SINGLE FAMILY DWELLING. WORK PER WFPP.
- Permit Issued
- Issued on 6/13/2024
- Issuing Office
- Valley
- Current Status
- Issued on 6/13/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2024 | GIOVANNY CHAVEZ |
| Corrections Issued | 6/12/2024 | GIOVANNY CHAVEZ |
| Issued | 6/13/2024 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/12/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/13/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/12/2024 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 7/15/2024 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 7/15/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 7/15/2024 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2024 | Partial Approval | ARUTYUN MADATYAN |
| Green Building Rough | 8/19/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Rough-Elec/Plmb/HVAC | 8/19/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 9/4/2024 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 9/4/2024 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 9/4/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 9/4/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 9/4/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 12/24/2024 | Corrections Issued | LOUIS ESCOTO |
| Interior/Exterior Lathing | 12/24/2024 | Approved | LOUIS ESCOTO |
| Insulation | 4/11/2025 | Approved | NICHOLAS TROWBRIDGE |
| Wood Frame | 4/11/2025 | Approved | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 6/6/2025 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 6/6/2025 | Approved | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 4/2/2026 | Approved | CHRISTOPHER ROJAS |
| Final | 4/2/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 4/2/2026 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 4/2/2026 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 4/2/2026 | Approved | CHRISTOPHER ROJAS |