8324 N SHARP AVE 91352
Certificate Information: 8324 N SHARP AVE 91352
- Application / Permit
- 24014-20000-02537
- Plan Check / Job No.
- B24VN08265
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: GARAGE CONVERSION TO ADU WITH ADDITION PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 2/5/2025
- Issuing Office
- Current Status
- CofO Issued on 10/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/18/2024 | GURUNATH NESARAJAH |
| Corrections Issued | 6/19/2024 | GURUNATH NESARAJAH |
| Plan Check Approved | 2/4/2025 | PINANK PATEL |
| Issued | 2/5/2025 | APPLICANT |
| CofO in Progress | 9/15/2025 | MATTHEW NELSON |
| CofO Issued | 10/14/2025 | RUBEN SALAS |
| Permit Finaled | 10/14/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/29/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 6/29/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 7/1/2024 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/3/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/3/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/26/2025 | Partial Approval | MATTHEW NELSON |
| Underground Mechanical | 2/28/2025 | Partial Approval | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 3/4/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 3/6/2025 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 4/4/2025 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 4/4/2025 | Approved | MATTHEW NELSON |
| HVAC-Rough | 4/4/2025 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 4/4/2025 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/14/2025 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 4/23/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 4/23/2025 | Partial Approval | MICHAEL CORTEZ |
| Drywall Nailing | 4/29/2025 | Approved | LOUIS ESCOTO |
| Shower Pan | 6/2/2025 | Approved | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 6/2/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 6/24/2025 | Approved | MATTHEW NELSON |
| Sewer | 6/24/2025 | Approved | MATTHEW NELSON |
| Sewer | 6/27/2025 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 9/4/2025 | Approved | MATTHEW NELSON |
| Final | 9/4/2025 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 9/4/2025 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 9/4/2025 | Approved | MATTHEW NELSON |
| Final | 9/12/2025 | OK to Issue CofO | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 9/12/2025 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 9/12/2025 | Approved | MATTHEW NELSON |