6107 N FARMDALE AVE 91606
Certificate Information: 6107 N FARMDALE AVE 91606
- Application / Permit
- 24014-20000-02526
- Plan Check / Job No.
- B24VN08222
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Existing detached garage to be converted into an ADU plus addition to ADU per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 2/25/2025
- Issuing Office
- Current Status
- CofO Issued on 4/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/14/2024 | NEHEMIAS RAMOS |
| Corrections Issued | 6/15/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 8/15/2024 | NGHI SU |
| Applicant returned to address corrections | 12/16/2024 | NEHEMIAS RAMOS |
| Plan Check Approved | 12/19/2024 | CARLOS MONTES |
| Issued | 2/25/2025 | APPLICANT |
| CofO in Progress | 3/26/2026 | ROBERTO PALACIOS-LOPEZ |
| CofO Issued | 4/9/2026 | RUBEN SALAS |
| Permit Finaled | 4/9/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/6/2024 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 8/6/2024 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/8/2024 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 8/8/2024 | MARKOS PEREZ-BRAN |
| Construction within easement | Cleared | 12/9/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Total Construction Resources; Lic. No.: 1067441-B | , |
| Contractor | Total Services Inc; Lic. No.: 1067441-B | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/24/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 4/14/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Deputy Drilled-In Anchors | 4/21/2025 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 4/23/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 4/23/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2025 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Sewer | 6/10/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 6/10/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 6/20/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 6/20/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 8/8/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 8/8/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 8/8/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 8/8/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 8/15/2025 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 8/15/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 8/15/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 8/15/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 8/15/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 8/22/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 8/22/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 8/22/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Insulation | 8/22/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 8/22/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 8/29/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 8/29/2025 | Partial Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 8/29/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 8/29/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 8/29/2025 | Partial Inspection | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 9/4/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 9/4/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 9/4/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 9/4/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 9/15/2025 | Approved | JAVIER RAMOS JR |
| Shower Pan | 10/3/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 10/10/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 10/10/2025 | Partial Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 3/4/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 3/4/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 3/4/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 3/4/2026 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 3/4/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 3/13/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 3/13/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 3/13/2026 | SGSOV Not Required | ROBERTO PALACIOS-LOPEZ |
| Final | 3/18/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 3/18/2026 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Final | 3/26/2026 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 3/26/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 3/26/2026 | Approved | ROBERTO PALACIOS-LOPEZ |