21619 W BLACKHAWK ST 91311

Certificate Information: 21619 W BLACKHAWK ST 91311

Application / Permit
24014-20000-02522
Plan Check / Job No.
B24VN08200
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Second story irregular shaped addition of 23' 10" x 20' 2". All work done per engineer.
Permit Issued
Issued on 9/24/2024
Issuing Office
Valley
Current Status
CofO Issued on 10/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/11/2024 APPLICANT
Assigned to Plan Check Engineer 6/27/2024 NAREG ATARIAN
Corrections Issued 7/2/2024 NAREG ATARIAN
Quality Review Completed 7/10/2024 OMID HEDAYAT
Building Plans Picked Up 7/12/2024 APPLICANT
Applicant returned to address corrections 8/26/2024 NAREG ATARIAN
Plan Check Approved 9/24/2024 NAREG ATARIAN
Issued 9/24/2024 APPLICANT
CofO in Progress 6/2/2025 JEFFREY HARTLINE
Permit Finaled 10/8/2025 JOHN JANSON
CofO Issued 10/8/2025 JOHN JANSON
Permit Finaled 10/8/2025 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/17/2024 CARLOS RAMIREZ
Grading Pre-Inspection Cleared 7/17/2024 CHARLES POWELL
Sewer availability Cleared 7/22/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 7/24/2024 CARLOS RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Telian,, Vartan; Lic. No.: C94330 11776 PIERCE ST      SYLMAR, CA 91342

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 1/24/2025 Conditional Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 2/4/2025 Approved JEFFREY HARTLINE
Footing/Foundation/Slab 2/4/2025 Approved JEFFREY HARTLINE
Sewer 2/4/2025 Partial Approval JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 2/19/2025 Corrections Issued JOHN COLEMAN
Wood Frame 2/19/2025 Partial Approval JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 3/12/2025 Partial Approval JEFFREY HARTLINE
Special/Order Compliance 3/12/2025 Corrections Issued JEFFREY HARTLINE
Underground Mechanical 3/12/2025 Approved JEFFREY HARTLINE
Deputy Drilled-In Anchors 3/21/2025 Conditional Approval CHRIS CHRISTENSEN
Interior/Exterior Lathing 4/2/2025 Partial Approval SCOTT SOBEL
ELECTRICAL-Rough 4/7/2025 Approved CHRIS CHRISTENSEN
HVAC-Rough 4/7/2025 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 4/7/2025 Approved CHRIS CHRISTENSEN
Wood Frame 4/7/2025 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 4/16/2025 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 4/16/2025 Approved JEFFREY HARTLINE
Green Building Rough 4/16/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 4/16/2025 Partial Approval JEFFREY HARTLINE
Shower Pan 4/16/2025 Approved JEFFREY HARTLINE
HVAC-Final 4/21/2025 Not Ready for Inspection JEFFREY HARTLINE
Insulation 4/21/2025 Approved JEFFREY HARTLINE
Drywall Nailing 4/25/2025 Approved JEFFREY PARD
Final 5/21/2025 Corrections Issued JEFFREY HARTLINE
Green Building Final 5/21/2025 Not Ready for Inspection JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 5/21/2025 SGSOV Approved JEFFREY HARTLINE
Smoke Detectors 5/21/2025 Approved JEFFREY HARTLINE
ELECTRICAL-Final 5/30/2025 Approved JEFFREY HARTLINE
Final 5/30/2025 OK to Issue CofO JEFFREY HARTLINE
Green Building Final 5/30/2025 Approved JEFFREY HARTLINE
HVAC-Final 5/30/2025 Approved JEFFREY HARTLINE