8135 N ANDASOL AVE 91325
Certificate Information: 8135 N ANDASOL AVE 91325
- Application / Permit
- 24014-20000-02505
- Plan Check / Job No.
- B24VN08126
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Two story irregular shaped 22'2" x 40' addition. NFPA 13D sprinkler required. All work done per engineer.
- Permit Issued
- Issued on 10/9/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/20/2024 | NAREG ATARIAN |
| Corrections Issued | 6/23/2024 | NAREG ATARIAN |
| Quality Review Completed | 7/1/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 7/2/2024 | APPLICANT |
| Applicant returned to address corrections | 9/11/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 10/3/2024 | NAREG ATARIAN |
| Plan Check Approved | 10/9/2024 | NAREG ATARIAN |
| Issued | 10/9/2024 | APPLICANT |
| CofO in Progress | 10/8/2025 | GAREN HAYRAPETYAN |
| Permit Finaled | 10/16/2025 | RUBEN SALAS |
| CofO Issued | 10/16/2025 | RUBEN SALAS |
| Permit Finaled | 10/16/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 7/25/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 7/25/2024 | BIAINA HARITUNIAN |
Contact Information
| Architect | Gomez,, Leonardo; Lic. No.: C30238 | 4342 ALLA ROAD LOS ANGELES, CA 90066 |
| Contractor | Owner-Builder | , |
| Engineer | Parikh,, Naman; Lic. No.: C91894 | 3450 SAWTELLE BLVD LOS ANGELES, CA 90066 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/29/2024 | Approved | SALVADOR MARTINEZ |
| Special/Order Compliance | 10/29/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Sewer | 11/27/2024 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 12/4/2024 | Corrections Issued | GAREN HAYRAPETYAN |
| Deputy Drilled-In Anchors | 12/12/2024 | Conditional Approval | RAUL OLAGI |
| PLUMBING-Rough | 12/16/2024 | Partial Approval | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 12/23/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 1/13/2025 | Approved | SALVADOR MARTINEZ |
| Deputy Wood Construction | 1/15/2025 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2025 | Partial Approval | SALVADOR MARTINEZ |
| Wood Frame | 2/11/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2025 | Partial Approval | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 3/28/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 3/28/2025 | Partial Approval | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 4/3/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| HVAC-Rough | 4/3/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 4/3/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Shower Pan | 4/3/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 4/10/2025 | Conditional Approval | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 4/15/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Gas Test | 4/15/2025 | Partial Approval | SALVADOR MARTINEZ |
| HVAC-Rough | 4/15/2025 | Approved | SALVADOR MARTINEZ |
| Underground Mechanical | 4/15/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Gas Test | 4/17/2025 | Partial Approval | SALVADOR MARTINEZ |
| Underground Mechanical | 4/17/2025 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 5/22/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Deck | 5/22/2025 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Rough | 5/22/2025 | Approved | SALVADOR MARTINEZ |
| Insulation | 5/30/2025 | Approved | SALVADOR MARTINEZ |
| Drywall Nailing | 6/10/2025 | Approved | MICHAEL CORTEZ |
| Green Building Rough | 6/10/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 6/10/2025 | Approved | MICHAEL CORTEZ |
| Special/Order Compliance | 6/10/2025 | Corrections Issued | MICHAEL CORTEZ |
| Service/Power Release | 9/11/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Service/Power Release | 9/16/2025 | Partial Inspection | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 9/25/2025 | Approved | WAYNE REGESTER |
| Final | 9/25/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Final | 9/25/2025 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 9/25/2025 | SGSOV Approved | WAYNE REGESTER |
| Smoke Detectors | 9/25/2025 | Approved | WAYNE REGESTER |
| Final | 10/1/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Final | 10/8/2025 | OK to Issue CofO | GAREN HAYRAPETYAN |