8311-8315 S KITTYHAWK AVE 90045

Certificate Information: 8311-8315 S KITTYHAWK AVE 90045

Application / Permit
24014-20000-02493
Plan Check / Job No.
B24VN08092
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT PORTION OF FRONT UNIT (8313) OF EXISTING DUPLEX (8313-8315) INTO ACCESSORY DWELLING UNIT (8311) PER LAMC 12.22A33(c) & (e). PROPOSED 12'4"X30'9" ADDITION TO THE FRONT UNIT W/4'X3' FRONT PORCH ADDN. PROPOSED 5'7/8"X14'6-1/4" PORCH ADDN TO THE REAR UNIT (8315). PROPOSED INT & EXT REMODEL TO EX DEPLEX PER PLAN. WORK PER ENGINEERED DESIGN.
Permit Issued
Issued on 7/1/2024
Issuing Office
Valley
Current Status
CofO Issued on 10/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/7/2024 APPLICANT
Assigned to Plan Check Engineer 6/14/2024 HAYATO TSUCHIYA
Corrections Issued 6/15/2024 HAYATO TSUCHIYA
Building Plans Picked Up 6/18/2024 APPLICANT
Applicant returned to address corrections 6/28/2024 ISIS ARGUETA
Plan Check Approved 7/1/2024 OMAR GARNICA
Issued 7/1/2024 APPLICANT
CofO in Progress 10/22/2024 BOBBY KEY
Permit Finaled 10/22/2024 RICHARD STEINBACH
CofO Issued 10/22/2024 RICHARD STEINBACH
Permit Finaled 10/22/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 6/21/2024 ANTHONY MAINEZ
Sewer availability Cleared 6/21/2024 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 6/24/2024 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 6/24/2024 HISASHI KOBAYAKAWA
Specific Plan Cleared 6/28/2024 RICHARD WOO

Contact Information

Contractor Owner-Builder       ,
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/26/2024 Conditional Approval BOBBY KEY
Footing/Foundation/Slab 7/3/2024 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 7/12/2024 Partial Approval BOBBY KEY
PLUMBING-Rough 7/12/2024 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 7/16/2024 Partial Approval BOBBY KEY
ELECTRICAL-Rough 8/2/2024 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 8/2/2024 Corrections Issued BOBBY KEY
PLUMBING-Rough 8/2/2024 Corrections Issued BOBBY KEY
Deputy Wood Construction 8/5/2024 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 8/5/2024 Approved BOBBY KEY
Shower Pan 8/5/2024 Approved BOBBY KEY
BUILDING-Rough-Frame 8/7/2024 Approved BOBBY KEY
ELECTRICAL-Rough 8/7/2024 Approved BOBBY KEY
Green Building Rough 8/7/2024 Approved BOBBY KEY
HVAC-Rough 8/7/2024 Approved BOBBY KEY
Interior/Exterior Lathing 8/7/2024 Partial Approval BOBBY KEY
PLUMBING-Rough 8/7/2024 Not Ready for Inspection BOBBY KEY
Insulation 8/12/2024 Approved BOBBY KEY
Interior/Exterior Lathing 8/12/2024 Approved BOBBY KEY
PLUMBING-Rough 8/12/2024 Corrections Issued BOBBY KEY
Drywall Nailing 8/16/2024 Approved BOBBY KEY
PLUMBING-Rough 8/16/2024 Approved BOBBY KEY
ELECTRICAL-Final 10/11/2024 Corrections Issued BOBBY KEY
Final 10/11/2024 Corrections Issued BOBBY KEY
Gas Test 10/11/2024 Approved BOBBY KEY
Green Building Final 10/11/2024 Approved BOBBY KEY
PLUMBING-Final 10/11/2024 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 10/11/2024 SGSOV Approved BOBBY KEY
Smoke Detectors 10/11/2024 Approved BOBBY KEY
ELECTRICAL-Final 10/18/2024 Corrections Issued BOBBY KEY
Final 10/18/2024 Not Ready for Inspection BOBBY KEY
HVAC-Final 10/18/2024 Corrections Issued BOBBY KEY
ELECTRICAL-Final 10/22/2024 Approved BOBBY KEY
Final 10/22/2024 OK to Issue CofO BOBBY KEY
HVAC-Final 10/22/2024 Approved BOBBY KEY