16140-16142 W MAYALL ST 91343

Certificate Information: 16140-16142 W MAYALL ST 91343

Application / Permit
24014-20000-02476
Plan Check / Job No.
B24VN08049
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Addition to and conversion of (E) detached garage to an ADU (per CA Govt. Code 65852.2(e)(1)(A)) with attached SB-9 unit per SB9 Two-Unit Development (Ca Govt Code 65852.21)
Permit Issued
Issued on 4/12/2025
Issuing Office
Current Status
CofO Issued on 12/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/6/2024 APPLICANT
Assigned to Plan Check Engineer 6/20/2024 HOOMAN HAJIZADEH
Corrections Issued 7/10/2024 HOOMAN HAJIZADEH
Quality Review Completed 7/11/2024 KAVIAN REFAHI
Applicant returned to address corrections 11/19/2024 HOOMAN HAJIZADEH
Applicant returned to address corrections 12/3/2024 HOOMAN HAJIZADEH
Applicant returned to address corrections 1/7/2025 HOOMAN HAJIZADEH
Applicant returned to address corrections 1/22/2025 HOOMAN HAJIZADEH
Applicant returned to address corrections 2/12/2025 HOOMAN HAJIZADEH
Applicant returned to address corrections 3/7/2025 HOOMAN HAJIZADEH
Plan Check Approved 4/8/2025 HOOMAN HAJIZADEH
Issued 4/12/2025 APPLICANT
CofO in Progress 11/21/2025 KEVIN BERBERYAN
CofO Issued 12/18/2025 RUBEN SALAS
Permit Finaled 12/18/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/7/2024 RYAN CASTRO
Construction near power lines Cleared 8/7/2024 WALTER RAMIREZ
Roof/Waste drainage to street Cleared 8/7/2024 RYAN CASTRO
Senate Bill 9 Cleared 8/12/2024 ASHLEY RODARTE
Eng Process Fee Ord 176,300 Cleared 9/27/2024 RYAN CASTRO
Sewer availability Cleared 10/9/2024 RYAN CASTRO
Grading Pre-Inspection Cleared 10/9/2024 CHARLES POWELL
Hydrant and Access approval Cleared 10/17/2024 JERRY KAO
Miscellaneous Cleared 10/28/2024 GREGORIO GUILLERMO
GPI Written Notices Cleared 1/7/2025 HOOMAN HAJIZADEH

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/6/2025 Corrections Issued CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 5/16/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Underground Mechanical 5/16/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 7/1/2025 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 8/6/2025 Corrections Issued CHRISTOPHER ROJAS
Deputy Wood Construction 8/6/2025 Conditional Approval JOAQUIN GREENOUGH
ELECTRICAL-Rough 8/6/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 8/6/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 8/6/2025 Approved CHRISTOPHER ROJAS
Underground Mechanical 8/6/2025 Partial Approval CHRISTOPHER ROJAS
Insulation 8/8/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Interior/Exterior Lathing 8/8/2025 Corrections Issued CHRISTOPHER ROJAS
Insulation 9/2/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Insulation 9/4/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 9/11/2025 Corrections Issued NICHOLAS TROWBRIDGE
Shower Pan 9/11/2025 Approved NICHOLAS TROWBRIDGE
Drywall Nailing 9/15/2025 Partial Approval CHRISTOPHER ROJAS
Final 9/15/2025 Corrections Issued CHRISTOPHER ROJAS
Interior/Exterior Lathing 9/18/2025 No Access for Inspection CHRISTOPHE COCHRAN
Interior/Exterior Lathing 9/19/2025 Approved CHRISTOPHER ROJAS
Underground Mechanical 10/23/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 11/3/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 11/3/2025 Corrections Issued CHRISTOPHER ROJAS
Final 11/3/2025 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 11/3/2025 Approved CHRISTOPHER ROJAS
Green Building Final 11/3/2025 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 11/3/2025 SGSOV No Gas CHRISTOPHER ROJAS
Smoke Detectors 11/3/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 11/6/2025 Approved KEVIN BERBERYAN
Final 11/6/2025 OK to Issue CofO KEVIN BERBERYAN
Service/Power Release 11/6/2025 Approved KEVIN BERBERYAN