6842 N CEDROS AVE 91405

Certificate Information: 6842 N CEDROS AVE 91405

Application / Permit
24014-20000-02467
Plan Check / Job No.
B24VN08012
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition of 12' x 35' in the east of the lot to the Single Family Dwelling, and remove all interior doors. NFPA 13D sprinkler required. All work done per engineer.
Permit Issued
Issued on 10/10/2024
Issuing Office
Valley
Current Status
CofO Issued on 10/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/6/2024 APPLICANT
Assigned to Plan Check Engineer 6/13/2024 NAREG ATARIAN
Corrections Issued 6/16/2024 NAREG ATARIAN
Quality Review Completed 6/17/2024 OMID HEDAYAT
Building Plans Picked Up 6/17/2024 APPLICANT
Applicant returned to address corrections 8/30/2024 NAREG ATARIAN
Applicant returned to address corrections 9/24/2024 NAREG ATARIAN
Plan Check Approved 10/1/2024 NAREG ATARIAN
Issued 10/10/2024 APPLICANT
CofO in Progress 10/29/2025 RYAN SALAZAR
Permit Finaled 10/29/2025 RUBEN SALAS
CofO Issued 10/29/2025 RUBEN SALAS
Permit Finaled 10/29/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/21/2024 TAL SHEMEN
Sewer availability Cleared 6/21/2024 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 6/25/2024 TAL SHEMEN

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/2/2024 Conditional Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 12/3/2024 Corrections Issued GAREN HAYRAPETYAN
Footing/Foundation/Slab 12/3/2024 Not Ready for Inspection GAREN HAYRAPETYAN
Excavation/Setback/Form/Re-Bar 12/13/2024 Approved RYAN SALAZAR
Footing/Foundation/Slab 12/13/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 12/18/2024 Partial Approval RYAN SALAZAR
Wood Frame 12/18/2024 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 12/19/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 1/7/2025 Approved RYAN SALAZAR
Deputy Wood Construction 1/8/2025 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 3/17/2025 Approved RYAN SALAZAR
HVAC-Rough 3/17/2025 Approved RYAN SALAZAR
PLUMBING-Rough 3/17/2025 Approved RYAN SALAZAR
Insulation 3/28/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 3/28/2025 Partial Approval RYAN SALAZAR
Shower Pan 3/28/2025 Approved RYAN SALAZAR
Drywall Nailing 4/4/2025 Approved RYAN SALAZAR
Green Building Rough 4/4/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 4/29/2025 Approved RYAN SALAZAR
BUILDING-Rough-Frame 10/22/2025 Approved RYAN SALAZAR
Final 10/22/2025 Corrections Issued RYAN SALAZAR
Green Building Final 10/22/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 10/22/2025 SGSOV Approved RYAN SALAZAR
Smoke Detectors 10/22/2025 Approved RYAN SALAZAR
Final 10/30/2025 OK to Issue CofO RYAN SALAZAR
Service/Power Release 10/30/2025 Approved RYAN SALAZAR