6537 W 84TH PL 90045
Certificate Information: 6537 W 84TH PL 90045
- Application / Permit
- 24014-20000-02450
- Plan Check / Job No.
- B24VN07956
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND REMODEL THROUGHOUT (E) SFD
- Permit Issued
- Issued on 9/10/2024
- Issuing Office
- Current Status
- CofO Issued on 12/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 6/13/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 6/13/2024 | APPLICANT |
| Plan Check Approved | 9/10/2024 | YAQUB MIRZA |
| Issued | 9/10/2024 | APPLICANT |
| CofO in Progress | 12/30/2025 | ANTHONY EGSON |
| Permit Finaled | 12/30/2025 | RICHARD STEINBACH |
| CofO Issued | 12/30/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/30/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/15/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2024 | DARIN LAM |
| Specific Plan | Cleared | 8/2/2024 | PEDRO AYALA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tangonan,, Jeffrey Tolentino; Lic. No.: C83522 | 17770 CAPE JASMINE RD CANYON COUNTRY, CA 91387 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/24/2024 | Conditional Approval | TEMISTOCLES CAAL |
| Pre-Inspection | 10/25/2024 | Partial Inspection | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 10/30/2024 | Approved | MICHAEL ALLEN |
| Footing/Foundation/Slab | 10/30/2024 | Conditional Approval | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2024 | Partial Approval | MICHAEL ALLEN |
| Footing/Foundation/Slab | 11/13/2024 | Approved | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2024 | Partial Approval | MICHAEL ALLEN |
| Insulation | 11/14/2024 | Partial Approval | MICHAEL ALLEN |
| ELECTRICAL-Rough | 1/17/2025 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2025 | Approved | JESUS RODRIGUEZ |
| Gas Test | 1/17/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 1/17/2025 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 1/17/2025 | Partial Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 1/24/2025 | Approved | MICHAEL ALLEN |
| Gas Test | 1/24/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| PLUMBING-Rough | 1/24/2025 | Conditional Approval | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 1/28/2025 | Approved | MICHAEL ALLEN |
| Gas Test | 1/28/2025 | Approved | MICHAEL ALLEN |
| Green Building Rough | 1/28/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 1/28/2025 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 2/10/2025 | Partial Approval | EVAN COOPER |
| Shower Pan | 2/10/2025 | Approved | EVAN COOPER |
| HVAC-Rough | 4/2/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Insulation | 4/2/2025 | Not Ready for Inspection | RUBEN RIVAS |
| HVAC-Rough | 4/4/2025 | Approved | RUBEN RIVAS |
| Insulation | 4/4/2025 | Approved | RUBEN RIVAS |
| BUILDING-Rough-Frame | 4/11/2025 | Approved | JAYLIN GRAVITTE |
| Drywall Nailing | 4/11/2025 | Approved | JAYLIN GRAVITTE |
| Green Building Rough | 4/11/2025 | Approved | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 4/11/2025 | Approved | JAYLIN GRAVITTE |
| ELECTRICAL-Final | 9/24/2025 | Corrections Issued | RUBEN RIVAS |
| Final | 9/24/2025 | Corrections Issued | RUBEN RIVAS |
| Green Building Final | 9/24/2025 | Approved | RUBEN RIVAS |
| HVAC-Final | 9/24/2025 | Corrections Issued | RUBEN RIVAS |
| PLUMBING-Final | 9/24/2025 | Corrections Issued | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 9/24/2025 | SGSOV Not Ready | RUBEN RIVAS |
| Service/Power Release | 9/24/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Smoke Detectors | 9/24/2025 | Corrections Issued | RUBEN RIVAS |
| ELECTRICAL-Final | 12/16/2025 | Approved | ANTHONY EGSON |
| Final | 12/16/2025 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 12/16/2025 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 12/16/2025 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 12/16/2025 | SGSOV Approved | ANTHONY EGSON |
| Service/Power Release | 12/16/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 12/16/2025 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 12/19/2025 | Approved | ANTHONY EGSON |
| HVAC-Final | 12/19/2025 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 12/19/2025 | Approved | ANTHONY EGSON |
| Final | 12/29/2025 | OK to Issue CofO | ANTHONY EGSON |
| Service/Power Release | 12/29/2025 | Approved | ANTHONY EGSON |