13221 W HESBY ST 91423
Certificate Information: 13221 W HESBY ST 91423
- Application / Permit
- 24014-20000-02437
- Plan Check / Job No.
- B24VN07895
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and Major Remodel to existing 1 story Single Family Dwelling, only 1' 8" and 19' of exterior wall and foundation to remain on South and East portion of the lot. Rebuilt as 2 story (58' 9 1/2" x 38' 11" Irregular Shaped) Single Family Dwelling, with attached garage. NFPA 13D fire sprinklers throughout. All work done per engineer.
- Permit Issued
- Issued on 9/13/2024
- Issuing Office
- Current Status
- CofO Issued on 10/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2024 | NAREG ATARIAN |
| Corrections Issued | 6/12/2024 | NAREG ATARIAN |
| Quality Review Completed | 6/12/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 6/13/2024 | APPLICANT |
| Applicant returned to address corrections | 8/28/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 9/9/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 9/13/2024 | NAREG ATARIAN |
| Plan Check Approved | 9/13/2024 | NAREG ATARIAN |
| Issued | 9/13/2024 | APPLICANT |
| CofO in Progress | 10/10/2025 | OGANES TARAKHCHYAN |
| Permit Finaled | 10/29/2025 | RUBEN SALAS |
| Permit Finaled | 10/29/2025 | RUBEN SALAS |
| CofO Issued | 10/29/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/12/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/13/2024 | BIAINA HARITUNIAN |
| Permit | Cleared | 8/15/2024 | BIAINA HARITUNIAN |
| Trees in Parkway | Cleared | 8/15/2024 | ADALBERTO VERA |
Contact Information
| Contractor | E H D Builders Inc; Lic. No.: 1034101-B | 18375 VENTURA BLVD STE #122 TARZANA, CA 91356 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/19/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 11/22/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 11/27/2024 | Approved | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 12/4/2024 | Conditional Approval | RAUL OLAGI |
| Deputy Wood Construction | 12/13/2024 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 2/24/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 2/24/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 3/4/2025 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 3/4/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 3/28/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 3/28/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 3/28/2025 | Approved | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 4/2/2025 | Conditional Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 4/3/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 4/11/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Shower Pan | 4/11/2025 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/14/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 4/14/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Green Building Rough | 4/14/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Special/Order Compliance | 4/14/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 4/16/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 4/16/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Rough | 4/16/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Insulation | 4/21/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 4/21/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Drywall Nailing | 4/25/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 4/25/2025 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 4/29/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 5/1/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 5/13/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Final | 8/12/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Final | 8/12/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Final | 8/12/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 8/20/2025 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 8/20/2025 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 8/20/2025 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/28/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 8/28/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 8/28/2025 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 8/28/2025 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 8/28/2025 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 9/4/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 10/8/2025 | OK to Issue CofO | OGANES TARAKHCHYAN |