5751 N ENSIGN AVE 91601
Certificate Information: 5751 N ENSIGN AVE 91601
- Application / Permit
- 24014-20000-02399
- Plan Check / Job No.
- B24VN07780
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DETACHED GARAGE (288 SF) WITH 35' x 22'3" IRREG. SHAPED ADDITION (612 SF) TO NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 8/19/2024
- Issuing Office
- Current Status
- CofO Issued on 5/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/7/2024 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 6/10/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 7/18/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 7/31/2024 | KAMYAR EMAMI |
| Applicant returned to address corrections | 8/15/2024 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 8/16/2024 | MIROOSH KHACHATOORIAN |
| Issued | 8/19/2024 | APPLICANT |
| CofO in Progress | 4/30/2025 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 5/15/2025 | RUBEN SALAS |
| CofO Issued | 5/15/2025 | RUBEN SALAS |
| Permit Finaled | 5/15/2025 | RUBEN SALAS |
Permit Application Clearance Information
| CPC | Cleared | 6/24/2024 | ASHLEY RODARTE |
| Address approval | Cleared | 7/2/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 7/2/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 7/2/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/3/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Spazio La Designs; Lic. No.: 1006766-B | , |
| Engineer | Crook,, Barrett Cameron; Lic. No.: C57196 | 5306 MULHOLLAND DRIVE SUMMERVILLE, SC 29485 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/25/2024 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 10/8/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 10/31/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 11/5/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/2/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 1/15/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 1/15/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 1/15/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 1/15/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 1/15/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 1/15/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Sewer | 1/15/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 1/15/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Insulation | 1/27/2025 | Corrections Issued | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 1/27/2025 | Partial Approval | MICHAEL CORTEZ |
| Insulation | 1/30/2025 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 2/10/2025 | Approved | JOSE AVILA |
| Green Building Rough | 2/10/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 2/10/2025 | Approved | JOSE AVILA |
| Shower Pan | 2/10/2025 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 4/24/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 4/24/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 4/24/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 4/24/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 4/24/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 4/24/2025 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 4/24/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 4/24/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 4/28/2025 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 4/28/2025 | Approved | ROBERTO PALACIOS-LOPEZ |