5751 N ENSIGN AVE 91601

Certificate Information: 5751 N ENSIGN AVE 91601

Application / Permit
24014-20000-02399
Plan Check / Job No.
B24VN07780
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT (E) DETACHED GARAGE (288 SF) WITH 35' x 22'3" IRREG. SHAPED ADDITION (612 SF) TO NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 8/19/2024
Issuing Office
Current Status
CofO Issued on 5/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2024 APPLICANT
Assigned to Plan Check Engineer 6/7/2024 MIROOSH KHACHATOORIAN
Corrections Issued 6/10/2024 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 7/18/2024 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 7/31/2024 KAMYAR EMAMI
Applicant returned to address corrections 8/15/2024 MIROOSH KHACHATOORIAN
Plan Check Approved 8/16/2024 MIROOSH KHACHATOORIAN
Issued 8/19/2024 APPLICANT
CofO in Progress 4/30/2025 ROBERTO PALACIOS-LOPEZ
Permit Finaled 5/15/2025 RUBEN SALAS
CofO Issued 5/15/2025 RUBEN SALAS
Permit Finaled 5/15/2025 RUBEN SALAS

Permit Application Clearance Information

CPC Cleared 6/24/2024 ASHLEY RODARTE
Address approval Cleared 7/2/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 7/2/2024 BIAINA HARITUNIAN
Sewer availability Cleared 7/2/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 7/3/2024 BIAINA HARITUNIAN

Contact Information

Contractor Spazio La Designs; Lic. No.: 1006766-B       ,
Engineer Crook,, Barrett Cameron; Lic. No.: C57196 5306 MULHOLLAND DRIVE      SUMMERVILLE, SC 29485

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/25/2024 Approved MISAEL ESPARZA
PLUMBING-Rough 10/8/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 10/31/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 11/5/2024 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 12/17/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 1/2/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 1/15/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 1/15/2025 Approved ROBERTO PALACIOS-LOPEZ
Gas Test 1/15/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 1/15/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Rough 1/15/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 1/15/2025 Approved ROBERTO PALACIOS-LOPEZ
Sewer 1/15/2025 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 1/15/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Insulation 1/27/2025 Corrections Issued MICHAEL CORTEZ
Interior/Exterior Lathing 1/27/2025 Partial Approval MICHAEL CORTEZ
Insulation 1/30/2025 Approved MISAEL ESPARZA
Drywall Nailing 2/10/2025 Approved JOSE AVILA
Green Building Rough 2/10/2025 Approved JOSE AVILA
Interior/Exterior Lathing 2/10/2025 Approved JOSE AVILA
Shower Pan 2/10/2025 Approved JOSE AVILA
ELECTRICAL-Final 4/24/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 4/24/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 4/24/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Final 4/24/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 4/24/2025 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 4/24/2025 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 4/24/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 4/24/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 4/28/2025 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Service/Power Release 4/28/2025 Approved ROBERTO PALACIOS-LOPEZ