10955 N ELDORA AVE 91040
Certificate Information: 10955 N ELDORA AVE 91040
- Application / Permit
- 24014-20000-02385
- Plan Check / Job No.
- B24VN07758
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO SFD AND REMODEL.
- Permit Issued
- Issued on 6/24/2024
- Issuing Office
- Current Status
- CofO Issued on 12/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/7/2024 | SERGIO MUNIZ |
| Corrections Issued | 6/10/2024 | SERGIO MUNIZ |
| Applicant returned to address corrections | 6/13/2024 | SERGIO MUNIZ |
| Plan Check Approved | 6/18/2024 | SERGIO MUNIZ |
| Issued | 6/24/2024 | APPLICANT |
| CofO in Progress | 12/3/2024 | WILLIAM WREN |
| Permit Finaled | 12/19/2024 | RUBEN SALAS |
| CofO Issued | 12/19/2024 | RUBEN SALAS |
| Permit Finaled | 12/19/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/11/2024 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 6/11/2024 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 6/11/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/11/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 6/11/2024 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 6/12/2024 | CHARLES POWELL |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | U S Home Developers Inc; Lic. No.: 947505-B | , |
| Contractor | Us Home Developers Inc; Lic. No.: 947505-B | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/22/2024 | Corrections Issued | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 7/23/2024 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 7/24/2024 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/2/2024 | Partial Approval | MATTHEW NELSON |
| Deputy Wood Construction | 8/22/2024 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 8/23/2024 | Corrections Issued | WILLIAM WREN |
| ELECTRICAL-Rough | 8/23/2024 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2024 | Approved | WILLIAM WREN |
| Green Building Rough | 8/23/2024 | Not Ready for Inspection | WILLIAM WREN |
| PLUMBING-Rough | 8/23/2024 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 9/6/2024 | Approved | WILLIAM WREN |
| Green Building Rough | 9/6/2024 | Approved | WILLIAM WREN |
| Insulation | 9/17/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 9/17/2024 | Approved | MATTHEW NELSON |
| Drywall Nailing | 9/24/2024 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 9/24/2024 | Approved | LOUIS ESCOTO |
| Final | 11/15/2024 | Corrections Issued | WILLIAM WREN |
| Footing/Foundation/Slab | 11/15/2024 | Approved | WILLIAM WREN |
| Green Building Final | 11/15/2024 | Not Ready for Inspection | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 11/15/2024 | SGSOV Approved | WILLIAM WREN |
| Smoke Detectors | 11/15/2024 | Not Ready for Inspection | WILLIAM WREN |
| Final | 11/26/2024 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 11/26/2024 | Corrections Issued | WILLIAM WREN |
| Smoke Detectors | 11/26/2024 | Not Ready for Inspection | WILLIAM WREN |
| Final | 12/2/2024 | OK to Issue CofO | WILLIAM WREN |
| Green Building Final | 12/2/2024 | Approved | WILLIAM WREN |
| Smoke Detectors | 12/2/2024 | Approved | WILLIAM WREN |