7830 N LOUISE AVE 91325

Certificate Information: 7830 N LOUISE AVE 91325

Application / Permit
24014-20000-02378
Plan Check / Job No.
B24VN07730
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE (323 SQFT) INTO ADU W/ 1ST (133 SQFT) AND 2ND FLOOR (337 SQFT) ADDITION. PER LAMC 12.22 A.33(c)(d)
Permit Issued
Issued on 9/11/2024
Issuing Office
Valley
Current Status
CofO Issued on 5/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2024 APPLICANT
Assigned to Plan Check Engineer 6/6/2024 PETER MOSESIAN
Corrections Issued 6/8/2024 PETER MOSESIAN
Quality Review Completed 6/12/2024 OMID HEDAYAT
Building Plans Picked Up 6/14/2024 APPLICANT
Plan Check Approved 8/7/2024 PETER MOSESIAN
Issued 9/11/2024 APPLICANT
CofO in Progress 4/28/2026 GAREN HAYRAPETYAN
Permit Finaled 5/28/2026 RUBEN SALAS
CofO Issued 5/28/2026 RUBEN SALAS
Permit Finaled 5/28/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/17/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 6/17/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 7/9/2024 EDGAR ALCARAZ
Sewer availability Cleared 7/9/2024 EDGAR ALCARAZ

Contact Information

Contractor Megaberg Construction; Lic. No.: 1095595-B 1433 ROCK GLEN #13      GLENDALE, CA 91205
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/3/2024 Corrections Issued SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 12/24/2024 Partial Approval SALVADOR MARTINEZ
PLUMBING-Rough 12/24/2024 Partial Approval SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 1/9/2025 Corrections Issued SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 1/13/2025 Approved GAREN HAYRAPETYAN
Footing/Foundation/Slab 1/13/2025 Approved GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 4/2/2025 Partial Approval JACK KARGODORIAN
Green Building Rough 4/2/2025 Not Ready for Inspection JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 4/30/2025 Corrections Issued GAREN HAYRAPETYAN
Wood Frame 4/30/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 5/1/2025 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 5/5/2025 Approved SALVADOR MARTINEZ
Pre-Inspection 5/9/2025 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 5/22/2025 Not Ready for Inspection GAREN HAYRAPETYAN
ELECTRICAL-Rough 5/22/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Rough 5/22/2025 Not Ready for Inspection GAREN HAYRAPETYAN
PLUMBING-Rough 5/22/2025 Approved GAREN HAYRAPETYAN
Sewer 6/2/2025 Approved JAVIER RAMOS JR
Underground Mechanical 6/2/2025 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 6/11/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 6/11/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Rough 6/11/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
HVAC-Rough 6/11/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 6/18/2025 Not Ready for Inspection SALVADOR MARTINEZ
ELECTRICAL-Rough 6/24/2025 Corrections Issued SALVADOR MARTINEZ
Interior/Exterior Lathing 6/24/2025 Partial Approval SALVADOR MARTINEZ
BUILDING-Rough-Frame 7/1/2025 Conditional Approval SALVADOR MARTINEZ
ELECTRICAL-Rough 7/1/2025 Partial Approval SALVADOR MARTINEZ
Green Building Rough 7/1/2025 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 7/9/2025 Approved SALVADOR MARTINEZ
ELECTRICAL-Rough 7/9/2025 Approved SALVADOR MARTINEZ
Insulation 7/9/2025 Partial Approval SALVADOR MARTINEZ
Insulation 7/16/2025 Approved SALVADOR MARTINEZ
Drywall Nailing 7/24/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 7/24/2025 Approved LOUIS ESCOTO
Shower Pan 8/19/2025 Partial Approval SALVADOR MARTINEZ
Shower Pan 8/21/2025 Approved GAREN HAYRAPETYAN
Final 12/19/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 12/19/2025 Not Ready for Inspection GAREN HAYRAPETYAN
PLUMBING-Final 12/19/2025 Not Ready for Inspection GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 12/19/2025 SGSOV No Gas GAREN HAYRAPETYAN
Smoke Detectors 12/19/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 4/6/2026 Not Ready for Inspection GAREN HAYRAPETYAN
HVAC-Final 4/6/2026 Approved GAREN HAYRAPETYAN
PLUMBING-Final 4/6/2026 Not Ready for Inspection GAREN HAYRAPETYAN
Service/Power Release 4/6/2026 Not Ready for Inspection GAREN HAYRAPETYAN
Final 4/13/2026 Corrections Issued KIRK SANDERS
Green Building Final 4/13/2026 Approved KIRK SANDERS
Final 4/23/2026 Corrections Issued GAREN HAYRAPETYAN
Final 4/28/2026 OK to Issue CofO GAREN HAYRAPETYAN