680 E 45TH ST 90011
Certificate Information: 680 E 45TH ST 90011
- Application / Permit
- 24014-20000-02357
- Plan Check / Job No.
- B24VN07659
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan**Addition to existing SFD (rear bldg) ** see comments **
- Permit Issued
- Issued on 3/4/2025
- Issuing Office
- Current Status
- Issued on 3/4/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2024 | KAVIAN REFAHI |
| Corrections Issued | 6/11/2024 | KAVIAN REFAHI |
| Quality Review Completed | 6/20/2024 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 10/4/2024 | KAVIAN REFAHI |
| Applicant returned to address corrections | 11/4/2024 | KAVIAN REFAHI |
| Application Withdrawn-Void | 12/11/2024 | KAVIAN REFAHI |
| Re-Activate Application | 12/30/2024 | KAVIAN REFAHI |
| Applicant returned to address corrections | 1/7/2025 | KAVIAN REFAHI |
| Plan Check Approved | 3/3/2025 | KAVIAN REFAHI |
| Issued | 3/4/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/11/2024 | WALLIE JONG |
| Sewer availability | Cleared | 7/11/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 7/16/2024 | WALLIE JONG |
| Tenant Habitability Plan | Cleared | 11/25/2024 | HUGO GARRIDO GARZA |
| Roof/Waste drainage to street | Cleared | 12/2/2024 | WALLIE JONG |
| Community Plan Implem. Overlay | Cleared | 2/10/2025 | ANACANY HURTADO |
Contact Information
| Contractor | L A Developing Inc; Lic. No.: 1083426-B | , |
| Engineer | Yiu,, Siu; Lic. No.: S5801 | PO BOX 1752 TEMPLE CITY, CA 91780 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/14/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 3/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 3/17/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 3/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 3/18/2025 | Approved | ALEJANDRO DE ARTOLA |
| Sewer | 3/21/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Wood Frame | 3/21/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2025 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 4/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 4/24/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 4/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 4/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 4/24/2025 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 4/24/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 6/4/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 6/4/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 6/4/2025 | Approved | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 6/13/2025 | Approved | ALEJANDRO DE ARTOLA |
| Wood Frame | 6/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/11/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 9/29/2025 | Corrections Issued | SABAS ALONSO |
| BUILDING-Rough-Frame | 10/9/2025 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 10/9/2025 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 10/9/2025 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 10/14/2025 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 10/17/2025 | Corrections Issued | ANTHONY RAMOS |
| Drywall Nailing | 10/21/2025 | Approved | JOHN QUINTANILLA |
| Insulation | 10/21/2025 | Partial Inspection | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 10/31/2025 | Approved | ANTHONY RAMOS |
| ELECTRICAL-Final | 2/12/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 2/12/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/12/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 2/12/2026 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/18/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/18/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/25/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 2/25/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 2/25/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 2/25/2026 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/25/2026 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/25/2026 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 2/25/2026 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 2/25/2026 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 2/26/2026 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 3/3/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 3/3/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 3/3/2026 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 3/3/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 3/4/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |