11428-11430 N HASKELL AVE 91344
Certificate Information: 11428-11430 N HASKELL AVE 91344
- Application / Permit
- 24014-20000-02356
- Plan Check / Job No.
- B24VN07657
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Junior Accessory Dwelling Unit
- Work Description
- ePlan: CONVERSION PORTION OF (E) SFD TO JR ADU (441SF). ( NORTH EAST PORTION OF SFD)
- Permit Issued
- Issued on 4/29/2025
- Issuing Office
- Current Status
- CofO Issued on 7/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/7/2024 | ZAW HAN |
| Corrections Issued | 6/10/2024 | ZAW HAN |
| Applicant returned to address corrections | 7/10/2024 | LUKE GONZALES |
| Applicant returned to address corrections | 8/1/2024 | LUKE GONZALES |
| Applicant returned to address corrections | 8/24/2024 | ZAW HAN |
| Plan Check Approved | 8/26/2024 | ZAW HAN |
| Issued | 4/29/2025 | APPLICANT |
| CofO in Progress | 5/8/2026 | JENNIFER RABUCHIN |
| CofO Issued | 7/9/2026 | RUBEN SALAS |
| Permit Finaled | 7/9/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/26/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 6/26/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/29/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vartanian,, Albert; Lic. No.: C39989 | 1250 W GLENOAKS BLVD E355 GLENDALE, CA 91201 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/8/2025 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/8/2025 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 7/8/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 7/8/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/8/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 7/21/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/21/2025 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 8/5/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/5/2025 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 8/5/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/28/2026 | Approved | JENNIFER RABUCHIN |
| Final | 4/28/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 4/28/2026 | Approved | JENNIFER RABUCHIN |
| Insulation | 4/28/2026 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 4/28/2026 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 4/28/2026 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 5/5/2026 | Approved | JENNIFER RABUCHIN |
| Final | 5/5/2026 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 5/5/2026 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 5/5/2026 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 5/5/2026 | Approved | JENNIFER RABUCHIN |