16755 W TULSA ST 91344

Certificate Information: 16755 W TULSA ST 91344

Application / Permit
24014-20000-02352
Plan Check / Job No.
B24VN07655
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) W/ ATTACHED PATIO COVER (10'X16') **ePlan**
Permit Issued
Issued on 9/16/2024
Issuing Office
Current Status
CofO Issued on 7/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/30/2024 APPLICANT
Assigned to Plan Check Engineer 6/6/2024 NILOOFAR MEHRAIN
Corrections Issued 6/11/2024 NILOOFAR MEHRAIN
Quality Review Completed 6/18/2024 JASON HEALEY
Applicant returned to address corrections 8/22/2024 NILOOFAR MEHRAIN
Plan Check Approved 8/23/2024 NILOOFAR MEHRAIN
Issued 9/16/2024 APPLICANT
CofO in Progress 7/24/2025 RAUL OLAGI
Permit Finaled 7/30/2025 RUBEN SALAS
CofO Issued 7/30/2025 RUBEN SALAS
Permit Finaled 7/30/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/15/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 6/15/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/17/2024 CARLOS AGUILERA
Sewer availability Cleared 6/17/2024 CARLOS AGUILERA
Construction near power lines Cleared 8/8/2024 RIDWAN HARDY
Construction within easement Cleared 8/8/2024 RIDWAN HARDY

Contact Information

Contractor Megrabyan Builders Inc; Lic. No.: 1046845-B       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/2/2024 Partial Approval JAVIER RAMOS JR
Underground Mechanical 10/2/2024 Partial Approval JAVIER RAMOS JR
Service/Power Release 10/7/2024 Partial Inspection SALVADOR MARTINEZ
Footing/Foundation/Slab 10/8/2024 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 10/24/2024 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 11/4/2024 Corrections Issued JAVIER RAMOS JR
Pre-Inspection 11/4/2024 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 11/18/2024 Corrections Issued VINCENT HANLEY
HVAC-Rough 11/18/2024 Corrections Issued VINCENT HANLEY
Interior/Exterior Lathing 11/18/2024 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 11/18/2024 Corrections Issued VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/5/2024 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 12/5/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 12/5/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 12/16/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 12/16/2024 Approved MICHEL ABAJAN
Insulation 1/9/2025 Corrections Issued JAVIER RAMOS JR
Drywall Nailing 1/24/2025 Partial Inspection JAVIER RAMOS JR
Insulation 1/24/2025 Approved JAVIER RAMOS JR
Sewer 2/21/2025 Approved JAVIER RAMOS JR
Underground Mechanical 3/18/2025 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Final 4/11/2025 Corrections Issued NICHOLAS TROWBRIDGE
HVAC-Final 4/11/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Final 4/11/2025 Approved NICHOLAS TROWBRIDGE
Service/Power Release 4/11/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 4/17/2025 Approved NICHOLAS TROWBRIDGE
Final 4/17/2025 Corrections Issued NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 4/17/2025 SGSOV Approved NICHOLAS TROWBRIDGE
Service/Power Release 4/17/2025 Approved NICHOLAS TROWBRIDGE
Smoke Detectors 4/17/2025 Approved NICHOLAS TROWBRIDGE
Verify Sprinkler Sign Off 4/17/2025 Approved NICHOLAS TROWBRIDGE
Pre-Inspection 6/3/2025 Partial Approval CHRISTOPHER ROJAS
Final 6/9/2025 Corrections Issued CHRISTOPHER ROJAS
Final 6/27/2025 Corrections Issued RAUL OLAGI
Final 7/24/2025 OK to Issue CofO RAUL OLAGI