8406 N AURA AVE 91324
Certificate Information: 8406 N AURA AVE 91324
- Application / Permit
- 24014-20000-02348
- Plan Check / Job No.
- B24VN07653
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan Major remodel of an existing single family dwelling with attached patio cover. All work per an engineered design.
- Permit Issued
- Issued on 7/26/2024
- Issuing Office
- Current Status
- CofO in Progress on 9/10/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/5/2024 | DANIEL SMILEY |
| Corrections Issued | 6/6/2024 | DANIEL SMILEY |
| Applicant returned to address corrections | 6/26/2024 | JOSE VELAZQUEZ |
| Applicant returned to address corrections | 7/17/2024 | ADAM HEGAZI |
| Plan Check Approved | 7/25/2024 | TSE MING HUANG |
| Issued | 7/26/2024 | APPLICANT |
| CofO in Progress | 7/2/2025 | CHRIS CHRISTENSEN |
| No Progress | 9/10/2025 | HENRY KIM |
| CofO in Progress | 9/10/2025 | HENRY KIM |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/15/2024 | CARLOS AGUILERA |
| ZA Case | Cleared | 6/17/2024 | DORIAN AGUILAR |
| Eng Process Fee Ord 176,300 | Cleared | 7/5/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | United Team Construction Inc; Lic. No.: 982005-B | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/22/2024 | Partial Approval | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 10/25/2024 | Corrections Issued | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 10/31/2024 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2024 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 11/19/2024 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 12/2/2024 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 1/22/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 1/22/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 1/29/2025 | Corrections Issued | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 1/29/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 2/6/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 2/11/2025 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 2/14/2025 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 2/14/2025 | Approved | CHRIS CHRISTENSEN |
| Insulation | 2/14/2025 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 2/14/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Drywall Nailing | 2/19/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 2/19/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Shower Pan | 2/19/2025 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 2/26/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 4/8/2025 | Approved | CHRIS CHRISTENSEN |
| Sewer | 4/8/2025 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 4/22/2025 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 4/22/2025 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 4/22/2025 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 4/28/2025 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 5/19/2025 | Approved | CHRIS CHRISTENSEN |
| Final | 5/19/2025 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 5/19/2025 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 5/19/2025 | Approved | CHRIS CHRISTENSEN |
| Final | 5/22/2025 | Conditional Approval | CHRIS CHRISTENSEN |
| Special/Order Compliance | 5/28/2025 | Corrections Issued | CHRIS CHRISTENSEN |
| Final | 7/1/2025 | OK to Issue CofO | CHRIS CHRISTENSEN |