17926 W CALIFA ST 91316
Certificate Information: 17926 W CALIFA ST 91316
- Application / Permit
- 24014-20000-02329
- Plan Check / Job No.
- B24VN07616
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major remodel and addition of one story irregular shaped 27' 8" x 44' 1" to the Single Family Dwelling. NFPA 13D sprinkler required. All work done per engineer.
- Permit Issued
- Issued on 8/8/2024
- Issuing Office
- Valley
- Current Status
- Issued on 8/8/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2024 | NAREG ATARIAN |
| Corrections Issued | 6/9/2024 | NAREG ATARIAN |
| Quality Review Completed | 6/11/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 6/13/2024 | APPLICANT |
| Plan Check Approved | 8/8/2024 | NAREG ATARIAN |
| Issued | 8/8/2024 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/12/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/12/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2024 | BIAINA HARITUNIAN |
| ZI | Cleared | 6/21/2024 | JASON CHAN |
| Trees in Parkway | Cleared | 7/8/2024 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 8/5/2024 | RUEL COLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/3/2024 | Corrections Issued | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 9/9/2024 | Corrections Issued | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 9/12/2024 | Corrections Issued | MORRIS JACKSON |
| Footing/Foundation/Slab | 9/13/2024 | No Access for Inspection | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 9/19/2024 | Corrections Issued | MORRIS JACKSON |
| Footing/Foundation/Slab | 10/15/2024 | Approved | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2024 | Partial Approval | MORRIS JACKSON |
| PLUMBING-Rough | 11/14/2024 | Not Ready for Inspection | MORRIS JACKSON |
| Gas Test | 11/20/2024 | Approved | MORRIS JACKSON |
| PLUMBING-Rough | 11/20/2024 | Partial Approval | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2024 | Partial Approval | MORRIS JACKSON |
| Insulation | 12/5/2024 | Partial Approval | MORRIS JACKSON |
| Interior/Exterior Lathing | 3/17/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 4/16/2025 | Corrections Issued | MORRIS JACKSON |
| Interior/Exterior Lathing | 7/2/2025 | Corrections Issued | MORRIS JACKSON |
| BUILDING-Rough-Frame | 8/4/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Green Building Rough | 8/4/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Interior/Exterior Lathing | 8/4/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Rough-Elec/Plmb/HVAC | 8/4/2025 | Corrections Issued | MORRIS JACKSON |
| Verify Sprinkler Sign Off | 8/4/2025 | Not Ready for Inspection | MORRIS JACKSON |
| BUILDING-Rough-Frame | 9/8/2025 | Corrections Issued | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2025 | Partial Approval | MORRIS JACKSON |
| Interior/Exterior Lathing | 9/8/2025 | Partial Approval | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2025 | Not Ready for Inspection | MORRIS JACKSON |
| PLUMBING-Rough | 9/10/2025 | Corrections Issued | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2025 | Partial Approval | MORRIS JACKSON |
| PLUMBING-Rough | 9/12/2025 | Approved | MORRIS JACKSON |
| HVAC-Rough | 9/22/2025 | Corrections Issued | MORRIS JACKSON |
| HVAC-Rough | 9/25/2025 | No Access for Inspection | MORRIS JACKSON |
| BUILDING-Rough-Frame | 10/17/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Green Building Rough | 10/17/2025 | Not Ready for Inspection | MORRIS JACKSON |
| HVAC-Rough | 10/17/2025 | Corrections Issued | MORRIS JACKSON |
| Insulation | 10/17/2025 | No Access for Inspection | MORRIS JACKSON |
| MERV13>=Rough | 10/17/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Verify Sprinkler Sign Off | 10/17/2025 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 10/22/2025 | Approved | MORRIS JACKSON |
| ELECTRICAL-Rough | 10/22/2025 | Approved | MORRIS JACKSON |
| Green Building Rough | 10/22/2025 | Approved | MORRIS JACKSON |
| HVAC-Rough | 10/22/2025 | Approved | MORRIS JACKSON |
| Insulation | 10/22/2025 | Approved | MORRIS JACKSON |
| Special/Order Compliance | 10/22/2025 | Partial Inspection | SEAN WIRCH |
| Drywall Nailing | 11/10/2025 | Approved | MORRIS JACKSON |