6418 W 85TH PL 90045

Certificate Information: 6418 W 85TH PL 90045

Application / Permit
24014-20000-02319
Plan Check / Job No.
B24VN07581
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE WITH 22'-2" x 14'ADDITION TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 8/7/2024
Issuing Office
Current Status
CofO Issued on 6/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/30/2024 APPLICANT
Assigned to Plan Check Engineer 6/6/2024 JESSE ARELLANO
Corrections Issued 6/6/2024 JESSE ARELLANO
Building Plans Picked Up 6/11/2024 APPLICANT
Plan Check Approved 7/3/2024 MIROOSH KHACHATOORIAN
Issued 8/7/2024 APPLICANT
CofO in Progress 5/28/2025 RUBEN RIVAS
Permit Finaled 6/6/2025 RICHARD STEINBACH
CofO Issued 6/6/2025 RICHARD STEINBACH
Permit Finaled 6/6/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 6/7/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 6/10/2024 DARIN LAM
Sewer availability Cleared 6/10/2024 DARIN LAM
Roof/Waste drainage to street Cleared 6/12/2024 DARIN LAM
Specific Plan Cleared 7/2/2024 FREDDY GARCIA

Contact Information

Contractor La Family Builders Inc ; Lic. No.: 1120579-B 6355 TOPANGA CANYON BLVD UNIT 331      WOODLAND HIILS, CA 91367
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/1/2024 Partial Approval TEMISTOCLES CAAL
Deputy Drilled-In Anchors 10/4/2024 Conditional Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 10/8/2024 Corrections Issued TEMISTOCLES CAAL
Underground Mechanical 10/8/2024 Corrections Issued TEMISTOCLES CAAL
Excavation/Setback/Form/Re-Bar 10/9/2024 Partial Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 10/9/2024 Partial Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 10/17/2024 Approved TEMISTOCLES CAAL
Sewer 10/17/2024 Approved TEMISTOCLES CAAL
Underground Mechanical 10/17/2024 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 11/13/2024 Not Ready for Inspection MICHAEL ALLEN
Deputy Wood Construction 11/13/2024 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 11/13/2024 Partial Approval MICHAEL ALLEN
Green Building Rough 11/13/2024 Not Ready for Inspection MICHAEL ALLEN
HVAC-Rough 11/13/2024 Corrections Issued MICHAEL ALLEN
PLUMBING-Rough 11/13/2024 Corrections Issued MICHAEL ALLEN
Wood Frame 11/13/2024 Corrections Issued MICHAEL ALLEN
BUILDING-Rough-Frame 11/22/2024 Conditional Approval MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 11/22/2024 Approved MICHAEL ALLEN
Gas Test 11/22/2024 Approved MICHAEL ALLEN
Rough-Elec/Plmb/HVAC 11/22/2024 Corrections Issued MICHAEL ALLEN
ELECTRICAL-Rough 11/26/2024 Approved MICHAEL ALLEN
Interior/Exterior Lathing 11/26/2024 Partial Approval MICHAEL ALLEN
PLUMBING-Rough 11/26/2024 Approved MICHAEL ALLEN
Wood Frame 11/26/2024 Approved MICHAEL ALLEN
HVAC-Rough 12/5/2024 Approved MICHAEL ALLEN
Insulation 12/5/2024 Approved MICHAEL ALLEN
Drywall Nailing 12/10/2024 Approved MICHAEL ALLEN
Interior/Exterior Lathing 12/19/2024 Approved MICHAEL ALLEN
Shower Pan 12/19/2024 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 3/21/2025 SGSOV Not Ready RUBEN RIVAS
BUILDING-Rough-Frame 4/2/2025 Not Ready for Inspection BOBBY KEY
Green Building Rough 4/2/2025 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 4/2/2025 SGSOV Not Ready BOBBY KEY
Final 4/3/2025 Corrections Issued RUBEN RIVAS
BUILDING-Rough-Frame 4/4/2025 Approved RUBEN RIVAS
ELECTRICAL-Final 4/4/2025 Approved RUBEN RIVAS
Final 4/4/2025 Not Ready for Inspection RUBEN RIVAS
Green Building Final 4/4/2025 Approved RUBEN RIVAS
HVAC-Final 4/4/2025 Approved RUBEN RIVAS
PLUMBING-Final 4/4/2025 Partial Approval RUBEN RIVAS
SGSOV-Seismic Gas S/O Valve 4/4/2025 SGSOV Not Ready RUBEN RIVAS
Service/Power Release 4/4/2025 Not Ready for Inspection RUBEN RIVAS
Smoke Detectors 4/4/2025 Approved RUBEN RIVAS
ELECTRICAL-Final 4/16/2025 Approved RUBEN RIVAS
Final 4/16/2025 Corrections Issued RUBEN RIVAS
HVAC-Final 4/16/2025 Approved RUBEN RIVAS
PLUMBING-Final 4/16/2025 Approved RUBEN RIVAS
SGSOV-Seismic Gas S/O Valve 4/16/2025 SGSOV Approved RUBEN RIVAS
Final 5/27/2025 OK to Issue CofO RUBEN RIVAS