17040 W HARTLAND ST 91406
Certificate Information: 17040 W HARTLAND ST 91406
- Application / Permit
- 24014-20000-02316
- Plan Check / Job No.
- B24VN07568
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND ADD 3'-6" X 12'-0" LAUNDRY ROOM AND STORAGE ADDITION.
- Permit Issued
- Issued on 10/22/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2024 | JESSE ARELLANO |
| Corrections Issued | 6/5/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 6/6/2024 | APPLICANT |
| Plan Check Approved | 10/3/2024 | ARAMIK SHAHMIRZAIAN |
| Issued | 10/22/2024 | APPLICANT |
| CofO in Progress | 6/3/2025 | MICKEY YAMASHITA |
| Permit Finaled | 6/5/2025 | DAVID JAMES |
| CofO Issued | 6/5/2025 | DAVID JAMES |
| Permit Finaled | 6/5/2025 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 6/8/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 6/8/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 9/25/2024 | TINA MIRANDA |
| Eng Process Fee Ord 176,300 | Cleared | 10/3/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 10/3/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Valencia,, Byron Steve; Lic. No.: C87372 | 16000 VENTURA BLVD., PH 1203 ENCINO, CA 91436 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/25/2024 | Not Ready for Inspection | JON MCHUGH |
| BUILDING-Rough-Frame | 10/28/2024 | Corrections Issued | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 10/28/2024 | Corrections Issued | MICKEY YAMASHITA |
| PLUMBING-Rough | 10/28/2024 | Corrections Issued | MICKEY YAMASHITA |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2024 | Not Ready for Inspection | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 10/31/2024 | Corrections Issued | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 11/26/2024 | Corrections Issued | MICKEY YAMASHITA |
| Gas Test | 11/26/2024 | Corrections Issued | MICKEY YAMASHITA |
| PLUMBING-Rough | 11/26/2024 | Partial Approval | MICKEY YAMASHITA |
| Insulation | 12/9/2024 | Partial Approval | MICKEY YAMASHITA |
| Wood Frame | 12/9/2024 | Corrections Issued | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 12/17/2024 | Conditional Approval | MICKEY YAMASHITA |
| ELECTRICAL-Rough | 12/17/2024 | Corrections Issued | MICKEY YAMASHITA |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2024 | Approved | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 12/17/2024 | Approved | MICKEY YAMASHITA |
| Green Building Rough | 12/17/2024 | Not Ready for Inspection | MICKEY YAMASHITA |
| HVAC-Rough | 12/17/2024 | Not Ready for Inspection | MICKEY YAMASHITA |
| Insulation | 12/17/2024 | Partial Approval | MICKEY YAMASHITA |
| PLUMBING-Rough | 12/17/2024 | Conditional Approval | MICKEY YAMASHITA |
| Sewer | 12/17/2024 | Not Ready for Inspection | MICKEY YAMASHITA |
| Interior/Exterior Lathing | 12/23/2024 | Approved | MICKEY YAMASHITA |
| Sewer | 1/9/2025 | Approved | MICKEY YAMASHITA |
| Gas Test | 1/23/2025 | Partial Approval | MICKEY YAMASHITA |
| Underground Mechanical | 1/23/2025 | Approved | MICKEY YAMASHITA |
| ELECTRICAL-Rough | 4/1/2025 | Partial Inspection | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 4/22/2025 | Conditional Approval | MICKEY YAMASHITA |
| ELECTRICAL-Final | 4/22/2025 | Corrections Issued | MICKEY YAMASHITA |
| Green Building Final | 4/22/2025 | Corrections Issued | MICKEY YAMASHITA |
| Green Building Rough | 4/22/2025 | Corrections Issued | MICKEY YAMASHITA |
| HVAC-Final | 4/22/2025 | Corrections Issued | MICKEY YAMASHITA |
| SGSOV-Seismic Gas S/O Valve | 4/22/2025 | SGSOV Approved | MICKEY YAMASHITA |
| Smoke Detectors | 4/22/2025 | Corrections Issued | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 4/29/2025 | Approved | MICKEY YAMASHITA |
| Final | 4/29/2025 | Partial Inspection | MICKEY YAMASHITA |
| Green Building Final | 4/29/2025 | Approved | MICKEY YAMASHITA |
| Green Building Rough | 4/29/2025 | Approved | MICKEY YAMASHITA |
| Smoke Detectors | 4/29/2025 | Conditional Approval | MICKEY YAMASHITA |
| Final | 6/3/2025 | OK to Issue CofO | MICKEY YAMASHITA |
| Smoke Detectors | 6/3/2025 | Approved | MICKEY YAMASHITA |