5900 N COSTELLO AVE 91401

Certificate Information: 5900 N COSTELLO AVE 91401

Application / Permit
24014-20000-02314
Plan Check / Job No.
B24VN07561
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) SFD FOR NEW MASTER BEDROOM, BATHROOM AND CLOSET. REMODEL KITCHEN/ DINING/ LIVING ROOM, AND BATHROOM.
Permit Issued
Issued on 1/20/2026
Issuing Office
Valley
Current Status
Issued on 1/20/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/29/2024 APPLICANT
Assigned to Plan Check Engineer 6/5/2024 ARTIN ZARUKIAN
Corrections Issued 6/8/2024 ARTIN ZARUKIAN
Building Plans Picked Up 6/11/2024 APPLICANT
Plan Check Approved 7/12/2024 ISIS ARGUETA
Issued 1/20/2026 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/10/2024 BIAINA HARITUNIAN
Sewer availability Cleared 6/10/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 6/24/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/26/2026 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 2/25/2026 Partial Approval MATTHEW NELSON
PLUMBING-Rough 2/25/2026 Partial Approval MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 3/9/2026 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 5/5/2026 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 5/5/2026 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 5/5/2026 Approved VINCENT HANLEY
Gas Test 5/5/2026 Approved VINCENT HANLEY
PLUMBING-Rough 5/5/2026 Approved VINCENT HANLEY
Deputy Wood Construction 5/18/2026 Conditional Approval JOSE AVILA
BUILDING-Rough-Frame 5/19/2026 Approved VINCENT HANLEY
Green Building Rough 5/19/2026 Approved VINCENT HANLEY
Interior/Exterior Lathing 5/19/2026 Partial Approval VINCENT HANLEY
Insulation 5/21/2026 Approved VINCENT HANLEY
Drywall Nailing 5/27/2026 Approved VINCENT HANLEY