17819 W DUNCAN ST 91316
Certificate Information: 17819 W DUNCAN ST 91316
- Application / Permit
- 24014-20000-02308
- Plan Check / Job No.
- B24VN07550
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- STORAGE ADDITION TO (E) DETACHED GARAGE.
- Permit Issued
- Issued on 7/7/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/5/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 6/8/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 6/11/2024 | APPLICANT |
| Applicant returned to address corrections | 6/24/2025 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 7/7/2025 | ROSENDO MEDINA |
| Issued | 7/7/2025 | APPLICANT |
| CofO in Progress | 1/5/2026 | ARUTYUN MADATYAN |
| Permit Finaled | 1/5/2026 | JOHN JANSON |
| CofO Issued | 1/5/2026 | JOHN JANSON |
| Permit Finaled | 1/5/2026 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/10/2024 | RYAN CASTRO |
| ZI | Cleared | 12/10/2024 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/11/2024 | RYAN CASTRO |
| Construction near power lines | Cleared | 2/4/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Stuhr,, Michael Patrick; Lic. No.: C30908 | 47331 GLENDALE ST CHILOQUIN, OR 97624 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/28/2025 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2025 | Approved | SEAN WIRCH |
| BUILDING-Rough-Frame | 11/17/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 11/17/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 11/17/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 11/17/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 12/4/2025 | Partial Approval | ARUTYUN MADATYAN |
| Drywall Nailing | 12/9/2025 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 12/29/2025 | Approved | ARUTYUN MADATYAN |
| Final | 12/29/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 12/29/2025 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 12/29/2025 | SGSOV Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 12/29/2025 | Approved | ARUTYUN MADATYAN |