4634 N ETHEL AVE 91423
Certificate Information: 4634 N ETHEL AVE 91423
- Application / Permit
- 24014-20000-02304
- Plan Check / Job No.
- B24VN07527
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- DEMO 2860 SF (E) SFD EXCEPT FOR 11'-6" OF FOUNDATION AT WESTERN PORTION TO REMAIN. REBUILD 55' X 63'-6" IRREGULAR SHAPED 2-STORY SFD W/ 2-CAR GARAGE. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 10/24/2024
- Issuing Office
- Current Status
- CofO Issued on 1/29/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2024 | RAPHAEL ROSAS |
| Corrections Issued | 6/10/2024 | RAPHAEL ROSAS |
| Quality Review Completed | 6/12/2024 | STEVEN KIM |
| Building Plans Picked Up | 6/18/2024 | APPLICANT |
| Applicant returned to address corrections | 7/3/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 7/10/2024 | RAPHAEL ROSAS |
| Issued | 10/24/2024 | APPLICANT |
| CofO in Progress | 12/29/2025 | CHRISTOPHE COCHRAN |
| Permit Finaled | 1/29/2026 | RUBEN SALAS |
| CofO Issued | 1/29/2026 | RUBEN SALAS |
| Permit Finaled | 1/29/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/11/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 6/11/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2024 | CARLOS RAMIREZ |
| Low Impact Development (LID) | Cleared | 6/12/2024 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 6/13/2024 | EDGAR ALCARAZ |
| Hydrant and Access approval | Cleared | 6/21/2024 | GILBERT URREA |
| ZI | Cleared | 6/21/2024 | DORIAN AGUILAR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/6/2024 | Approved | CHRISTOPHE COCHRAN |
| Underground Mechanical | 12/6/2024 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 12/13/2024 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Structural Steel Frame | 1/6/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2025 | Partial Approval | JACK KARGODORIAN |
| PLUMBING-Rough | 2/20/2025 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 3/6/2025 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 3/17/2025 | Corrections Issued | JACK KARGODORIAN |
| Green Building Rough | 3/17/2025 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 3/17/2025 | Approved | JACK KARGODORIAN |
| MERV13>=Rough | 3/17/2025 | Approved | JACK KARGODORIAN |
| Insulation | 3/27/2025 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 3/27/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Shower Pan | 3/27/2025 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 4/2/2025 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 4/2/2025 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 12/15/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Final | 12/15/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 12/15/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Service/Power Release | 12/15/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 12/23/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 12/23/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 12/23/2025 | Approved | CHRISTOPHE COCHRAN |
| MERV13>=Final | 12/23/2025 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 12/23/2025 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 12/23/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 12/29/2025 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Pre-Inspection | 12/29/2025 | Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 12/29/2025 | Approved | CHRISTOPHE COCHRAN |