13941 W CALIFA ST 91401
Certificate Information: 13941 W CALIFA ST 91401
- Application / Permit
- 24014-20000-02290
- Plan Check / Job No.
- B24VN07485
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMOVE 8'-6"X 10'-6" TOOL SHED, 23'-3" X 20'-1" ADDITION TO (E) DETACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g).
- Permit Issued
- Issued on 6/24/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 6/3/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 6/5/2024 | APPLICANT |
| Issued | 6/24/2024 | APPLICANT |
| CofO in Progress | 10/22/2025 | RYAN SALAZAR |
| CofO Issued | 11/13/2025 | RUBEN SALAS |
| Permit Finaled | 11/13/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/8/2024 | WALTER RAMIREZ |
| Address approval | Cleared | 6/10/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 6/10/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/24/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/28/2024 | Partial Approval | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 7/8/2024 | Approved | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 7/9/2024 | Conditional Approval | ROBERT GOLD |
| ELECTRICAL-Rough | 9/4/2024 | Approved | RYAN SALAZAR |
| HVAC-Rough | 9/4/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 9/4/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2024 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 9/6/2024 | Approved | RYAN SALAZAR |
| Green Building Rough | 9/6/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 9/6/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/10/2024 | Partial Approval | SALVADOR MARTINEZ |
| Drywall Nailing | 9/12/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/12/2024 | Approved | RYAN SALAZAR |
| Shower Pan | 9/12/2024 | Approved | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 12/13/2024 | Conditional Approval | RAUL OLAGI |
| Deputy Steel/Welding | 12/13/2024 | Conditional Approval | RAUL OLAGI |
| Deputy Steel/Welding | 1/6/2025 | Conditional Approval | RAUL OLAGI |
| Sewer | 1/22/2025 | Approved | RYAN SALAZAR |
| Underground Mechanical | 1/22/2025 | Approved | RYAN SALAZAR |
| Final | 6/24/2025 | Corrections Issued | RYAN SALAZAR |
| Footing/Foundation/Slab | 6/24/2025 | Approved | RYAN SALAZAR |
| Green Building Final | 6/24/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 6/24/2025 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 6/24/2025 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 6/24/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 6/25/2025 | Approved | RYAN SALAZAR |
| HVAC-Final | 6/25/2025 | Approved | RYAN SALAZAR |
| Final | 10/23/2025 | OK to Issue CofO | RYAN SALAZAR |
| Service/Power Release | 10/23/2025 | Approved | RYAN SALAZAR |