14108 W GRUEN ST 91331

Certificate Information: 14108 W GRUEN ST 91331

Application / Permit
24014-20000-02288
Plan Check / Job No.
B24VN07481
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT (E) DETACHED GARAGE + LEGALIZE UNPERMITTED ADDITION TO (N) 618 SF ADU PER GCS 65852.2(e)(1)(A). ALL WORK PER ENG. Existing construction that does not pose a threat to the publics health and safety was allowed per Government Code Section 55.852.2(d)(2).
Permit Issued
Issued on 11/21/2024
Issuing Office
Current Status
CofO Issued on 3/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/5/2024 APPLICANT
Assigned to Plan Check Engineer 6/10/2024 LUISANGEL VALENZUELA
Corrections Issued 6/11/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 8/31/2024 LUISANGEL VALENZUELA
Plan Check Approved 11/17/2024 LUISANGEL VALENZUELA
Issued 11/21/2024 APPLICANT
CofO in Progress 2/13/2025 MICHEL ABAJAN
Permit Finaled 3/4/2025 RUBEN SALAS
CofO Issued 3/4/2025 RUBEN SALAS
Permit Finaled 3/4/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/9/2024 MARKOS PEREZ-BRAN
Sewer availability Cleared 7/9/2024 MARKOS PEREZ-BRAN
Address approval Cleared 7/10/2024 MARKOS PEREZ-BRAN
Construction near power lines Cleared 11/1/2024 TINA MIRANDA
Construction within easement Cleared 11/1/2024 TINA MIRANDA

Contact Information

Contractor Schi Solutions Inc; Lic. No.: 1085283-B       ,
Engineer Tabar,, Mehrdad; Lic. No.: C37433 15402 CHERBOURG AVENUE      IRVINE, CA 92604

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/11/2024 Approved MICHEL ABAJAN
Footing/Foundation/Slab 12/11/2024 Approved MICHEL ABAJAN
Underground Mechanical 12/11/2024 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 12/27/2024 Corrections Issued SEAN HAUPT
ELECTRICAL-Rough 12/27/2024 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 12/27/2024 Corrections Issued SEAN HAUPT
HVAC-Rough 12/27/2024 Approved SEAN HAUPT
PLUMBING-Rough 12/27/2024 Approved SEAN HAUPT
Special/Order Compliance 12/27/2024 Approved SEAN HAUPT
BUILDING-Rough-Frame 1/2/2025 Approved MICHEL ABAJAN
Green Building Rough 1/2/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 1/8/2025 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 1/13/2025 Partial Approval MICHEL ABAJAN
Insulation 1/13/2025 Approved MICHEL ABAJAN
Drywall Nailing 1/16/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 2/10/2025 Approved MICHEL ABAJAN
Final 2/10/2025 Corrections Issued MICHEL ABAJAN
Green Building Final 2/10/2025 Approved MICHEL ABAJAN
HVAC-Final 2/10/2025 Approved MICHEL ABAJAN
PLUMBING-Final 2/10/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 2/10/2025 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 2/10/2025 Approved MICHEL ABAJAN
Final 2/12/2025 OK to Issue CofO MICHEL ABAJAN