8346 N WYSTONE AVE 91324
Certificate Information: 8346 N WYSTONE AVE 91324
- Application / Permit
- 24014-20000-02285
- Plan Check / Job No.
- B24VN07477
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan***PROPOSED ADDITION TO SINGLE FAMILY DWELLING; WORK TO INCLUDE REMOVING ATTACHED PATIO COVER
- Permit Issued
- Issued on 5/7/2025
- Issuing Office
- Current Status
- Issued on 5/7/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2024 | SINA KHOSRAVI |
| Corrections Issued | 6/25/2024 | SINA KHOSRAVI |
| Quality Review Completed | 7/16/2024 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 2/28/2025 | SINA KHOSRAVI |
| Plan Check Approved | 4/10/2025 | SINA KHOSRAVI |
| Plan Check Approved | 5/6/2025 | SINA KHOSRAVI |
| Issued | 5/7/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/26/2024 | BRYAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 10/26/2024 | BRYAN GODINEZ |
| Sewer availability | Cleared | 11/5/2024 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/13/2025 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castro,, Ivan; Lic. No.: C84846 | 750 OTAY LAKES ROAD #202 CHULA VISTA, CA 91910 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/1/2025 | Conditional Approval | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 8/4/2025 | Not Ready for Inspection | KRISTEN CAUSEY |
| PLUMBING-Rough | 8/4/2025 | Partial Approval | KRISTEN CAUSEY |
| Excavation/Setback/Form/Re-Bar | 8/8/2025 | Partial Approval | KRISTEN CAUSEY |
| Excavation/Setback/Form/Re-Bar | 8/15/2025 | Approved | DAVID SCANTLIN |
| Footing/Foundation/Slab | 8/15/2025 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2025 | Partial Approval | DAVID SCANTLIN |
| Deputy Wood Construction | 10/7/2025 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2025 | Partial Approval | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 11/18/2025 | Corrections Issued | DAVID SCANTLIN |
| ELECTRICAL-Rough | 11/18/2025 | Approved | DAVID SCANTLIN |
| Green Building Rough | 11/18/2025 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 11/18/2025 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 11/18/2025 | Partial Approval | DAVID SCANTLIN |
| PLUMBING-Rough | 11/18/2025 | Approved | DAVID SCANTLIN |
| Insulation | 12/1/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Shower Pan | 12/1/2025 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 12/9/2025 | Conditional Approval | KRISTEN CAUSEY |
| Insulation | 12/9/2025 | Conditional Approval | KRISTEN CAUSEY |
| Drywall Nailing | 12/18/2025 | Corrections Issued | DAVID SCANTLIN |