8346 N WYSTONE AVE 91324

Certificate Information: 8346 N WYSTONE AVE 91324

Application / Permit
24014-20000-02285
Plan Check / Job No.
B24VN07477
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan***PROPOSED ADDITION TO SINGLE FAMILY DWELLING; WORK TO INCLUDE REMOVING ATTACHED PATIO COVER
Permit Issued
Issued on 5/7/2025
Issuing Office
Current Status
Issued on 5/7/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/28/2024 APPLICANT
Assigned to Plan Check Engineer 6/13/2024 SINA KHOSRAVI
Corrections Issued 6/25/2024 SINA KHOSRAVI
Quality Review Completed 7/16/2024 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 2/28/2025 SINA KHOSRAVI
Plan Check Approved 4/10/2025 SINA KHOSRAVI
Plan Check Approved 5/6/2025 SINA KHOSRAVI
Issued 5/7/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/26/2024 BRYAN GODINEZ
Roof/Waste drainage to street Cleared 10/26/2024 BRYAN GODINEZ
Sewer availability Cleared 11/5/2024 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 2/13/2025 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Castro,, Ivan; Lic. No.: C84846 750 OTAY LAKES ROAD   #202    CHULA VISTA, CA 91910

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/1/2025 Conditional Approval DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 8/4/2025 Not Ready for Inspection KRISTEN CAUSEY
PLUMBING-Rough 8/4/2025 Partial Approval KRISTEN CAUSEY
Excavation/Setback/Form/Re-Bar 8/8/2025 Partial Approval KRISTEN CAUSEY
Excavation/Setback/Form/Re-Bar 8/15/2025 Approved DAVID SCANTLIN
Footing/Foundation/Slab 8/15/2025 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 9/5/2025 Partial Approval DAVID SCANTLIN
Deputy Wood Construction 10/7/2025 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 10/15/2025 Partial Approval KRISTEN CAUSEY
BUILDING-Rough-Frame 11/18/2025 Corrections Issued DAVID SCANTLIN
ELECTRICAL-Rough 11/18/2025 Approved DAVID SCANTLIN
Green Building Rough 11/18/2025 Approved DAVID SCANTLIN
HVAC-Rough 11/18/2025 Approved DAVID SCANTLIN
Interior/Exterior Lathing 11/18/2025 Partial Approval DAVID SCANTLIN
PLUMBING-Rough 11/18/2025 Approved DAVID SCANTLIN
Insulation 12/1/2025 Not Ready for Inspection DAVID SCANTLIN
Shower Pan 12/1/2025 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 12/9/2025 Conditional Approval KRISTEN CAUSEY
Insulation 12/9/2025 Conditional Approval KRISTEN CAUSEY
Drywall Nailing 12/18/2025 Corrections Issued DAVID SCANTLIN