9818-9820 N MARKLEIN AVE 91343

Certificate Information: 9818-9820 N MARKLEIN AVE 91343

Application / Permit
24014-20000-02280
Plan Check / Job No.
B24VN07466
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan - 2 STORY ADU (540 SF) / GARAGE ADDITION TO EXISITNG SFD W GARAGE PER 12.22 A33 C & E
Permit Issued
Issued on 10/28/2024
Issuing Office
Current Status
CofO Issued on 2/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/29/2024 APPLICANT
Assigned to Plan Check Engineer 6/13/2024 STARR CHEN
Corrections Issued 6/20/2024 STARR CHEN
Quality Review Completed 6/24/2024 EUGENE BARBEAU
Applicant returned to address corrections 8/28/2024 STARR CHEN
Applicant returned to address corrections 10/16/2024 STARR CHEN
Plan Check Approved 10/22/2024 STARR CHEN
Issued 10/28/2024 APPLICANT
CofO in Progress 2/12/2025 VINCENT HANLEY
Permit Finaled 2/18/2025 RUBEN SALAS
CofO Issued 2/18/2025 RUBEN SALAS
Permit Finaled 2/18/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/29/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 6/29/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/1/2024 CARLOS AGUILERA
Sewer availability Cleared 7/1/2024 CARLOS AGUILERA
Construction near power lines Cleared 8/23/2024 RIDWAN HARDY

Contact Information

Contractor Jdc Builders; Lic. No.: 1057617-B 14500 ROSCOE BLVD STE 400      PANORAMA CITY, CA 91402
Engineer Kazemi,, Milad; Lic. No.: C92143 28025 DOROTHY DR STE 202      AGOURA HILLS, CA 91301

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/7/2024 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 11/7/2024 Approved VINCENT HANLEY
Footing/Foundation/Slab 11/7/2024 Approved VINCENT HANLEY
PLUMBING-Rough 11/7/2024 Partial Approval VINCENT HANLEY
Sewer 11/7/2024 Approved VINCENT HANLEY
Deputy Reinf. Concrete 11/12/2024 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 11/18/2024 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 11/27/2024 Partial Approval VINCENT HANLEY
Interior/Exterior Lathing 11/27/2024 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 12/6/2024 Corrections Issued VINCENT HANLEY
HVAC-Rough 12/6/2024 Corrections Issued VINCENT HANLEY
Interior/Exterior Lathing 12/6/2024 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 12/6/2024 Approved VINCENT HANLEY
Shower Pan 12/6/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 12/9/2024 Partial Approval VINCENT HANLEY
Underground Mechanical 12/11/2024 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 12/17/2024 Approved VINCENT HANLEY
Green Building Rough 12/17/2024 Approved VINCENT HANLEY
HVAC-Rough 12/17/2024 Approved VINCENT HANLEY
Insulation 12/17/2024 Approved VINCENT HANLEY
MERV13>=Rough 12/17/2024 Approved VINCENT HANLEY
Drywall Nailing 12/23/2024 Approved RUBEN SALAS
ELECTRICAL-Final 2/6/2025 Approved VINCENT HANLEY
HVAC-Final 2/6/2025 Corrections Issued VINCENT HANLEY
PLUMBING-Final 2/6/2025 Approved VINCENT HANLEY
Final 2/11/2025 OK to Issue CofO VINCENT HANLEY
Green Building Final 2/11/2025 Approved VINCENT HANLEY
HVAC-Final 2/11/2025 Approved VINCENT HANLEY
MERV13>=Final 2/11/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 2/11/2025 SGSOV Approved VINCENT HANLEY
Service/Power Release 2/11/2025 Approved VINCENT HANLEY
Smoke Detectors 2/11/2025 Approved VINCENT HANLEY