19523-19527 W STAGG ST 91335
Certificate Information: 19523-19527 W STAGG ST 91335
- Application / Permit
- 24014-20000-02277
- Plan Check / Job No.
- B24VN07462
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN New attached ADU (816 S.F.) and conversion (E) garage to JADU (366 S.F.). ATTACHED ADU PER LAMC 12.22 A.33 (c) and (e). JADU PER 65852.2(e)(1)(A) and 65852.22. SEE COMMENTS.
- Permit Issued
- Issued on 12/19/2024
- Issuing Office
- Current Status
- CofO Issued on 8/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2024 | ADRIANA LOPEZ |
| Corrections Issued | 6/24/2024 | ADRIANA LOPEZ |
| Quality Review Completed | 7/8/2024 | SINA KHOSRAVI |
| Plan Check Approved | 12/18/2024 | ADRIANA LOPEZ |
| Issued | 12/19/2024 | APPLICANT |
| CofO in Progress | 8/1/2025 | JUAN ALVARADO |
| Permit Finaled | 8/10/2025 | RUBEN SALAS |
| CofO Issued | 8/10/2025 | RUBEN SALAS |
| Permit Finaled | 8/10/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/11/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/11/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 7/11/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/11/2024 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 7/19/2024 | ALEX VELA |
| Construction near power lines | Cleared | 11/3/2024 | TINA MIRANDA |
| Construction within easement | Cleared | 11/3/2024 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nguyen,, Chuc Ich; Lic. No.: NA38556 | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 1/14/2025 | Partial Approval | JEFFREY HARTLINE |
| Underground Mechanical | 1/14/2025 | Approved | JEFFREY HARTLINE |
| Deputy Drilled-In Anchors | 1/21/2025 | Approved | ARUTYUN MADATYAN |
| Excavation/Setback/Form/Re-Bar | 1/21/2025 | Approved | ARUTYUN MADATYAN |
| Structural Steel Frame | 1/21/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Gas Test | 1/29/2025 | Partial Approval | ARUTYUN MADATYAN |
| PLUMBING-Rough | 1/29/2025 | Partial Approval | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2025 | Approved | JUAN ALVARADO |
| BUILDING-Rough-Frame | 2/20/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2025 | Partial Approval | JUAN ALVARADO |
| Green Building Rough | 2/20/2025 | Not Ready for Inspection | JUAN ALVARADO |
| ELECTRICAL-Rough | 3/19/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 3/19/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 3/24/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Rough | 3/24/2025 | Approved | JUAN ALVARADO |
| BUILDING-Rough-Frame | 3/27/2025 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 3/27/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 3/27/2025 | Approved | ARUTYUN MADATYAN |
| Insulation | 4/4/2025 | Approved | MORRIS JACKSON |
| Shower Pan | 4/4/2025 | Approved | MORRIS JACKSON |
| Drywall Nailing | 4/10/2025 | Approved | ARUTYUN MADATYAN |
| Insulation | 4/10/2025 | Approved | ARUTYUN MADATYAN |
| Final | 5/20/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 5/20/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Final | 5/20/2025 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 5/20/2025 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Smoke Detectors | 5/20/2025 | Approved | ARUTYUN MADATYAN |
| Final | 5/28/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 5/28/2025 | SGSOV Approved | ARUTYUN MADATYAN |
| Final | 6/27/2025 | Partial Approval | JUAN ALVARADO |
| ELECTRICAL-Final | 7/3/2025 | Approved | JUAN ALVARADO |
| Final | 7/3/2025 | OK to Issue CofO | JUAN ALVARADO |
| HVAC-Final | 7/3/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 7/3/2025 | Approved | JUAN ALVARADO |