13265 1/2 W FILMORE ST 91331

Certificate Information: 13265 1/2 W FILMORE ST 91331

Application / Permit
24014-20000-02263
Plan Check / Job No.
B24VN07409
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Convert (E) detached garage to ADU with new addition per WFPP and per Ordinance (LAMC 12.22 A.33 (c)-(d))
Permit Issued
Issued on 3/17/2025
Issuing Office
Current Status
CofO Issued on 6/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/24/2024 APPLICANT
Assigned to Plan Check Engineer 6/28/2024 JOHNPAUL ISIP
Corrections Issued 7/1/2024 JOHNPAUL ISIP
Applicant returned to address corrections 2/5/2025 HOOMAN HAJIZADEH
Applicant returned to address corrections 2/21/2025 HOOMAN HAJIZADEH
Applicant returned to address corrections 2/27/2025 HOOMAN HAJIZADEH
Plan Check Approved 3/5/2025 HOOMAN HAJIZADEH
Issued 3/17/2025 APPLICANT
CofO in Progress 5/14/2026 MICHEL ABAJAN
Permit Finaled 6/5/2026 RUBEN SALAS
CofO Issued 6/5/2026 RUBEN SALAS
Permit Finaled 6/5/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/4/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 9/4/2024 EDGAR ALCARAZ
Clean Up Green Up Cleared 10/16/2024 DORIAN AGUILAR
Sewer availability Cleared 10/16/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 1/27/2025 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/26/2025 Partial Inspection MICHEL ABAJAN
PLUMBING-Rough 7/14/2025 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 7/16/2025 Approved MICHEL ABAJAN
METHANE-Barrier 7/16/2025 Approved MICHEL ABAJAN
METHANE-Subgrade 7/16/2025 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 9/2/2025 Approved MICHEL ABAJAN
ELECTRICAL-Rough 9/2/2025 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 9/2/2025 Partial Approval MICHEL ABAJAN
Green Building Rough 9/2/2025 Approved MICHEL ABAJAN
HVAC-Rough 9/2/2025 Approved MICHEL ABAJAN
METHANE-Rough 9/2/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 9/2/2025 Approved MICHEL ABAJAN
Insulation 9/10/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 9/10/2025 Approved MICHEL ABAJAN
Drywall Nailing 9/25/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Final 3/10/2026 Approved MICHEL ABAJAN
Final 3/10/2026 Corrections Issued MICHEL ABAJAN
Green Building Final 3/10/2026 Approved MICHEL ABAJAN
HVAC-Final 3/10/2026 Approved MICHEL ABAJAN
PLUMBING-Final 3/10/2026 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 3/10/2026 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 3/10/2026 Approved MICHEL ABAJAN
Final 5/11/2026 Not Ready for Inspection MICHEL ABAJAN
Final 5/13/2026 OK to Issue CofO MICHEL ABAJAN