7051 N LASAINE AVE 91406

Certificate Information: 7051 N LASAINE AVE 91406

Application / Permit
24014-20000-02258
Plan Check / Job No.
B24VN07401
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Addition and remodel to existing one story S.F.D. with attached garage.
Permit Issued
Issued on 6/17/2024
Issuing Office
Current Status
CofO Issued on 1/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/29/2024 APPLICANT
Assigned to Plan Check Engineer 5/30/2024 CAROLEAN BASMA
Corrections Issued 5/30/2024 CAROLEAN BASMA
Plan Check Approved 6/8/2024 CAROLEAN BASMA
Issued 6/17/2024 APPLICANT
CofO in Progress 12/31/2024 JON MCHUGH
Permit Finaled 1/2/2025 JOHN JANSON
CofO Issued 1/2/2025 JOHN JANSON
Permit Finaled 1/2/2025 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/3/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 6/3/2024 CARLOS AGUILERA

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Preferred Home Builders Inc; Lic. No.: 773147-B       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/20/2024 Corrections Issued MORRIS JACKSON
Deputy Drilled-In Anchors 8/21/2024 Conditional Approval MORRIS JACKSON
Footing/Foundation/Slab 8/26/2024 Approved MORRIS JACKSON
BUILDING-Rough-Frame 9/5/2024 Not Ready for Inspection MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 9/5/2024 Partial Approval MORRIS JACKSON
Green Building Rough 9/5/2024 Not Ready for Inspection MORRIS JACKSON
PLUMBING-Rough 9/5/2024 Partial Approval MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 9/10/2024 Partial Approval MORRIS JACKSON
Insulation 9/10/2024 Partial Approval MORRIS JACKSON
BUILDING-Rough-Frame 10/1/2024 Corrections Issued MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 10/1/2024 Partial Approval MORRIS JACKSON
Rough-Elec/Plmb/HVAC 10/2/2024 Not Ready for Inspection JON MCHUGH
Deputy Wood Construction 10/18/2024 Conditional Approval MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 10/18/2024 Partial Approval MORRIS JACKSON
Green Building Rough 10/18/2024 Not Ready for Inspection MORRIS JACKSON
Rough-Elec/Plmb/HVAC 10/18/2024 Not Ready for Inspection MORRIS JACKSON
ELECTRICAL-Rough 10/23/2024 Corrections Issued MORRIS JACKSON
HVAC-Rough 10/23/2024 Not Ready for Inspection MORRIS JACKSON
PLUMBING-Rough 10/23/2024 Approved MORRIS JACKSON
Rough-Elec/Plmb/HVAC 10/23/2024 Not Ready for Inspection MORRIS JACKSON
Wood Frame 10/23/2024 Not Ready for Inspection MORRIS JACKSON
Interior/Exterior Lathing 10/24/2024 Not Ready for Inspection MORRIS JACKSON
BUILDING-Rough-Frame 10/25/2024 Approved MORRIS JACKSON
Green Building Rough 10/25/2024 Approved MORRIS JACKSON
Interior/Exterior Lathing 10/25/2024 Partial Approval MORRIS JACKSON
Rough-Elec/Plmb/HVAC 10/25/2024 Approved MORRIS JACKSON
Insulation 10/29/2024 Approved ALEXANDER HANDY
Shower Pan 10/29/2024 Approved ALEXANDER HANDY
Drywall Nailing 11/1/2024 Not Ready for Inspection MORRIS JACKSON
Interior/Exterior Lathing 11/1/2024 Approved MORRIS JACKSON
Drywall Nailing 11/4/2024 Approved MORRIS JACKSON
Drywall Nailing 12/24/2024 Approved JOHN COLEMAN
ELECTRICAL-Final 12/24/2024 Corrections Issued JOHN COLEMAN
Final 12/24/2024 Not Ready for Inspection JOHN COLEMAN
Green Building Final 12/24/2024 Approved JOHN COLEMAN
HVAC-Final 12/24/2024 Corrections Issued JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 12/24/2024 SGSOV Not Ready JOHN COLEMAN
Smoke Detectors 12/24/2024 Approved JOHN COLEMAN
Final 12/27/2024 Corrections Issued JON MCHUGH
SGSOV-Seismic Gas S/O Valve 12/27/2024 SGSOV Approved JON MCHUGH
ELECTRICAL-Final 12/30/2024 Approved JON MCHUGH
Final 12/30/2024 OK to Issue CofO JON MCHUGH
HVAC-Final 12/30/2024 Approved JON MCHUGH
PLUMBING-Final 12/30/2024 Approved JON MCHUGH