851 1/2 W 48TH ST 90037

Certificate Information: 851 1/2 W 48TH ST 90037

Application / Permit
24014-20000-02249
Plan Check / Job No.
B24VN07373
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
10'-0" X 13'-4" ADDITION TO (E) DETACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 11/4/2024
Issuing Office
Valley
Current Status
CofO Issued on 8/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/24/2024 APPLICANT
Assigned to Plan Check Engineer 5/31/2024 ARTIN ZARUKIAN
Corrections Issued 6/1/2024 ARTIN ZARUKIAN
Building Plans Picked Up 6/4/2024 APPLICANT
Plan Check Approved 10/15/2024 KAMYAR EMAMI
Issued 11/4/2024 APPLICANT
CofO in Progress 7/31/2025 BARRY HACHE
Permit Finaled 8/7/2025 DEROLD HAUFF
CofO Issued 8/7/2025 DEROLD HAUFF
Permit Finaled 8/7/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/26/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 10/2/2024 JESSICA OPINION
Sewer availability Cleared 10/2/2024 JESSICA OPINION
Tenant Habitability Plan Cleared 10/7/2024 HUGO GARRIDO GARZA
Address approval Cleared 10/8/2024 CHRISTINA BRACO

Contact Information

Contractor Pnr Builders Inc; Lic. No.: 1028148-B 21226 VENTURA BLVD 250      WOODLAND HILLS, CA 91364
Engineer Mroczka,, Peter J; Lic. No.: C42648 9301 DARBY AVE APT 1      NORTHRIDGE, CA 91325

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/16/2025 Corrections Issued BARRY HACHE
PLUMBING-Rough 1/21/2025 Approved BARRY HACHE
Excavation/Setback/Form/Re-Bar 2/11/2025 Not Ready for Inspection BARRY HACHE
Excavation/Setback/Form/Re-Bar 2/19/2025 Approved NICHOLAS LOPEZ
Deputy Wood Construction 4/3/2025 Conditional Approval REGINA MENDEZ
Rough-Elec/Plmb/HVAC 4/4/2025 Corrections Issued BARRY HACHE
Rough-Elec/Plmb/HVAC 4/8/2025 Corrections Issued BARRY HACHE
BUILDING-Rough-Frame 4/10/2025 Not Ready for Inspection BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 4/10/2025 Approved BARRY HACHE
Rough-Elec/Plmb/HVAC 4/10/2025 Approved BARRY HACHE
Green Building Rough 4/17/2025 Corrections Issued BARRY HACHE
BUILDING-Rough-Frame 4/18/2025 Not Ready for Inspection BARRY HACHE
Interior/Exterior Lathing 4/18/2025 Corrections Issued BARRY HACHE
BUILDING-Rough-Frame 4/23/2025 Conditional Approval MICHAEL LEWIS
Green Building Rough 4/23/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 4/23/2025 Approved ANTHONY RAMOS
Insulation 4/30/2025 Corrections Issued BARRY HACHE
Insulation 5/5/2025 Approved ANTHONY RAMOS
Drywall Nailing 5/9/2025 Approved BARRY HACHE
Underground Mechanical 6/12/2025 Approved BARRY HACHE
Final 7/23/2025 Corrections Issued SABAS ALONSO
Green Building Final 7/23/2025 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 7/23/2025 SGSOV Approved SABAS ALONSO
Smoke Detectors 7/23/2025 Approved SABAS ALONSO
BUILDING-Rough-Frame 7/28/2025 Approved BARRY HACHE
Final 7/28/2025 Not Ready for Inspection BARRY HACHE
Footing/Foundation/Slab 7/28/2025 Approved BARRY HACHE
Final 7/31/2025 OK to Issue CofO BARRY HACHE