16243 W CHATSWORTH ST 91344
Certificate Information: 16243 W CHATSWORTH ST 91344
- Application / Permit
- 24014-20000-02244
- Plan Check / Job No.
- B24VN07362
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL OF (E) SFD, ENCLOSE 5' X 6'-4" REAR PORCH AND 4'-9" X 16'-7" FRONT PORCH, AND ADD 20' x 25' STORAGE. WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 7/2/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2024 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 6/3/2024 | MIROOSH KHACHATOORIAN |
| Building Plans Picked Up | 6/4/2024 | APPLICANT |
| Plan Check Approved | 6/21/2024 | ANGELICA MARTINEZ |
| Issued | 7/2/2024 | APPLICANT |
| CofO in Progress | 3/14/2025 | JAVIER RAMOS JR |
| No Progress | 3/27/2025 | JOAQUIN GREENOUGH |
| CofO in Progress | 3/27/2025 | JOAQUIN GREENOUGH |
| Permit Finaled | 5/23/2025 | RUBEN SALAS |
| CofO Issued | 5/23/2025 | RUBEN SALAS |
| Permit Finaled | 5/23/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/4/2024 | KENIA CASTILLO |
| Eng Process Fee Ord 176,300 | Cleared | 6/21/2024 | BRYAN GODINEZ |
Contact Information
| Contractor | New Look Construction Inc; Lic. No.: 1098333-B | 7837 LAUREL CANYON BLVD NORTH HOLLYWOOD, CA 91605 |
| Engineer | Valencia,, Byron Steve; Lic. No.: C87372 | 16000 VENTURA BLVD., PH 1203 ENCINO, CA 91436 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/22/2024 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 8/27/2024 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2024 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 8/27/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 8/27/2024 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 8/27/2024 | Approved | JAVIER RAMOS JR |
| Sewer | 8/27/2024 | Approved | JAVIER RAMOS JR |
| Deputy Wood Construction | 8/28/2024 | Conditional Approval | ROBERT GOLD |
| ELECTRICAL-Rough | 8/30/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 8/30/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 8/30/2024 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 9/5/2024 | Off-Hour Fees Due | |
| Interior/Exterior Lathing | 9/5/2024 | Off-Hour Fees Due | |
| Shower Pan | 9/5/2024 | Off-Hour Fees Due | |
| Drywall Nailing | 9/6/2024 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 9/6/2024 | Approved | KEVIN BERBERYAN |
| Shower Pan | 9/6/2024 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 1/14/2025 | Approved | ROBERT GOLD |
| BUILDING-Rough-Frame | 2/7/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 2/7/2025 | Approved | JAVIER RAMOS JR |
| Final | 2/7/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 2/7/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Rough | 2/7/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 2/7/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 2/7/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 2/7/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 2/7/2025 | Approved | JAVIER RAMOS JR |
| Final | 3/13/2025 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 3/13/2025 | Approved | JAVIER RAMOS JR |
| Special/Order Compliance | 3/27/2025 | Corrections Issued | JOAQUIN GREENOUGH |