2620 S NAPLES AVE 90291
Certificate Information: 2620 S NAPLES AVE 90291
- Application / Permit
- 24014-20000-02242
- Plan Check / Job No.
- B24VN07357
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 15' x 12' 6" addition on the North side of the property to enlarge the closet and provide new bathroom for the master bedroom. All work done per engineer.
- Permit Issued
- Issued on 10/7/2024
- Issuing Office
- Current Status
- CofO Issued on 4/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2024 | NAREG ATARIAN |
| Corrections Issued | 6/18/2024 | NAREG ATARIAN |
| Quality Review Completed | 6/21/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 7/3/2024 | APPLICANT |
| Plan Check Approved | 9/19/2024 | NAREG ATARIAN |
| Issued | 10/7/2024 | APPLICANT |
| CofO in Progress | 4/16/2025 | MICHAEL ALLEN |
| Permit Finaled | 4/21/2025 | RICHARD STEINBACH |
| CofO Issued | 4/21/2025 | RICHARD STEINBACH |
| Permit Finaled | 4/21/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/16/2024 | VLADIMIR ARUTYUNYAN |
| Roof/Waste drainage to street | Cleared | 7/16/2024 | DINAH GARIN |
| Sewer availability | Cleared | 7/16/2024 | VLADIMIR ARUTYUNYAN |
| Specific Plan | Cleared | 7/16/2024 | RICHARD WOO |
| Specific Plan | Cleared | 8/25/2024 | IRA BROWN |
| ZI | Cleared | 8/25/2024 | IRA BROWN |
| Miscellaneous | Cleared | 8/26/2024 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 8/26/2024 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 8/26/2024 | RUBEN VASQUEZ |
| Coastal Zone | Cleared | 9/10/2024 | ASHLEY RODARTE |
Contact Information
| Architect | Debolske,, Philip James; Lic. No.: C14694 | 5150 WILSHIRE BLVD SUITE 503 LOS ANGELES, CA 90036 |
| Contractor | Goldenline Construction Inc; Lic. No.: 989378-B | 1812 W BURBANK BLVD #201 BURBANK, CA 91506 |
| Engineer | Tan,, Henreik; Lic. No.: C65723 | 5100 LLANO DRIVE WOODLAND HILLS, CA 91364 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/28/2024 | Corrections Issued | JESUS PINEDA |
| BUILDING-Rough-Frame | 11/12/2024 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 11/12/2024 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2024 | Partial Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 11/13/2024 | Approved | JESUS PINEDA |
| Insulation | 11/13/2024 | Partial Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 11/22/2024 | Approved | REGINA MENDEZ |
| BUILDING-Rough-Frame | 11/26/2024 | Conditional Approval | BOBBY KEY |
| ELECTRICAL-Rough | 11/26/2024 | Approved | BOBBY KEY |
| Green Building Rough | 11/26/2024 | Approved | BOBBY KEY |
| HVAC-Rough | 11/26/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 11/26/2024 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 12/16/2024 | Approved | JESUS PINEDA |
| Insulation | 12/24/2024 | Approved | JESUS PINEDA |
| Shower Pan | 12/24/2024 | Corrections Issued | JESUS PINEDA |
| Drywall Nailing | 1/13/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 1/13/2025 | Approved | JESUS PINEDA |
| Shower Pan | 1/13/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 3/28/2025 | Corrections Issued | MICHAEL ALLEN |
| Final | 3/28/2025 | Partial Approval | MICHAEL ALLEN |
| Green Building Final | 3/28/2025 | Approved | MICHAEL ALLEN |
| HVAC-Final | 3/28/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 3/28/2025 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 3/28/2025 | SGSOV Approved | MICHAEL ALLEN |
| Smoke Detectors | 3/28/2025 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 4/2/2025 | Approved | MICHAEL ALLEN |
| Final | 4/15/2025 | OK to Issue CofO | MICHAEL ALLEN |