7763 N LOMA VERDE AVE 91304

Certificate Information: 7763 N LOMA VERDE AVE 91304

Application / Permit
24014-20000-02220
Plan Check / Job No.
B24VN07251
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 10/11/2024
Issuing Office
Current Status
CofO Issued on 6/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/22/2024 APPLICANT
Assigned to Plan Check Engineer 5/24/2024 JEROME MAGAT PALMA
Corrections Issued 5/25/2024 JEROME MAGAT PALMA
Building Plans Picked Up 5/29/2024 APPLICANT
Issued 10/11/2024 APPLICANT
CofO in Progress 3/14/2025 DAVID SCANTLIN
Permit Finaled 6/26/2025 JOHN JANSON
CofO Issued 6/26/2025 JOHN JANSON
Permit Finaled 6/26/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/2/2024 TAL SHEMEN
Roof/Waste drainage to street Cleared 6/2/2024 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 6/14/2024 TAL SHEMEN
Sewer availability Cleared 6/14/2024 TAL SHEMEN
Construction near power lines Cleared 10/4/2024 RIDWAN HARDY

Contact Information

Contractor Ivy Green Construction; Lic. No.: 1014647-B 14537 VENTURA BLVD      SHERMAN OAKS, CA 91403
Engineer Valencia,, Byron Steve; Lic. No.: C87372 16000 VENTURA BLVD., PH 1203      ENCINO, CA 91436

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/18/2024 Conditional Approval ARUTYUN MADATYAN
Footing/Foundation/Slab 10/21/2024 Approved ALEXANDER HANDY
PLUMBING-Rough 10/21/2024 Partial Approval ALEXANDER HANDY
Sewer 10/21/2024 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 12/2/2024 Partial Approval ALEXANDER HANDY
Green Building Rough 12/2/2024 Not Ready for Inspection ALEXANDER HANDY
Rough-Elec/Plmb/HVAC 12/2/2024 Conditional Approval ALEXANDER HANDY
Interior/Exterior Lathing 12/6/2024 No Access for Inspection GEVORK IPCHYAN
Interior/Exterior Lathing 12/11/2024 Partial Approval ALEXANDER HANDY
BUILDING-Rough-Frame 1/3/2025 Approved MORRIS JACKSON
Green Building Rough 1/3/2025 Approved MORRIS JACKSON
Insulation 1/3/2025 Approved MORRIS JACKSON
Drywall Nailing 1/10/2025 Approved JOHN COLEMAN
Final 2/20/2025 Corrections Issued ALEXANDER HANDY
Green Building Final 2/20/2025 Not Ready for Inspection ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 2/20/2025 SGSOV No Gas ALEXANDER HANDY
Smoke Detectors 2/20/2025 Approved ALEXANDER HANDY
ELECTRICAL-Final 3/13/2025 Approved DAVID SCANTLIN
Final 3/13/2025 OK to Issue CofO DAVID SCANTLIN
Green Building Final 3/13/2025 Approved DAVID SCANTLIN
HVAC-Final 3/13/2025 Approved DAVID SCANTLIN
PLUMBING-Final 3/13/2025 Approved DAVID SCANTLIN
Service/Power Release 3/13/2025 Approved DAVID SCANTLIN