13744 W BESSEMER ST 91401

Certificate Information: 13744 W BESSEMER ST 91401

Application / Permit
24014-20000-02219
Plan Check / Job No.
B24VN07247
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(1) Dwelling - Single Family
Work Description
REAR PATIO COVER ADDITION TO (E) SFD
Permit Issued
Issued on 7/11/2024
Issuing Office
Current Status
CofO Issued on 9/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/25/2024 APPLICANT
Assigned to Plan Check Engineer 5/31/2024 GURUNATH NESARAJAH
Corrections Issued 5/31/2024 GURUNATH NESARAJAH
Plan Check Approved 6/25/2024 GURUNATH NESARAJAH
Issued 7/11/2024 APPLICANT
CofO in Progress 9/16/2024 RYAN SALAZAR
Permit Finaled 9/25/2024 DANIEL ORRANTE
CofO Issued 9/25/2024 DANIEL ORRANTE
Permit Finaled 9/25/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/7/2024 JOHN LIN
Roof/Waste drainage to street Cleared 6/7/2024 JOHN LIN
"Q" conditions Cleared 6/12/2024 DORIAN AGUILAR
Metro Rail approval Cleared 6/18/2024 JENNIFER SU

Contact Information

Contractor Project Blue Construction Group; Lic. No.: 1099867-B       ,
Engineer Dominguez,, Refugio; Lic. No.: NA50820       ,
Engineer Wu,, Harold Ping-Hung; Lic. No.: C35693 1168 SAN GABRIEL BLVD NO N      ROSEMEAD, CA 91770

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/22/2024 Partial Inspection RYAN SALAZAR
Deputy Drilled-In Anchors 7/26/2024 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 7/29/2024 Partial Approval KEVIN BERBERYAN
ELECTRICAL-Rough 8/22/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 8/22/2024 Partial Approval RYAN SALAZAR
Deputy Wood Construction 8/23/2024 Conditional Approval JUAN VALENZUELA
Insulation 8/27/2024 Approved ROBERT GOLD
Interior/Exterior Lathing 8/27/2024 Approved ROBERT GOLD
BUILDING-Rough-Frame 9/13/2024 Approved RYAN SALAZAR
Final 9/13/2024 OK to Issue CofO RYAN SALAZAR
Footing/Foundation/Slab 9/13/2024 Approved RYAN SALAZAR
Smoke Detectors 9/13/2024 Approved RYAN SALAZAR