6108 N SADRING AVE 91367

Certificate Information: 6108 N SADRING AVE 91367

Application / Permit
24014-20000-02217
Plan Check / Job No.
B24VN07235
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ENCLOSE THE LOFT WITH ADDITION ON THE 2ND FLOOR . 42 SF OF STOAGE ADDITION ON THE FIRST FLOOR
Permit Issued
Issued on 7/11/2024
Issuing Office
Current Status
CofO Issued on 6/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/22/2024 APPLICANT
Assigned to Plan Check Engineer 5/23/2024 JOE VO
Corrections Issued 5/25/2024 JOE VO
Quality Review Completed 6/11/2024 GARO TELMI
Plan Check Approved 7/1/2024 JOE VO
Issued 7/11/2024 APPLICANT
CofO in Progress 4/3/2025 KIM BEAUCHAMP
Permit Finaled 6/11/2025 DAVID JAMES
CofO Issued 6/11/2025 DAVID JAMES
Permit Finaled 6/11/2025 DAVID JAMES

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/15/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/17/2024 CARLOS AGUILERA
Sewer availability Cleared 6/17/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: NA93079       ,

Inspector Information

JACK UPCHURCH, (818) 374-9853 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/15/2024 No Access for Inspection TROY SANDERS
Deputy Drilled-In Anchors 7/30/2024 Conditional Approval TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 8/21/2024 Corrections Issued JOEL GUARDADO
Footing/Foundation/Slab 11/4/2024 No Access for Inspection KIM BEAUCHAMP
Wood Frame 11/4/2024 No Access for Inspection KIM BEAUCHAMP
Footing/Foundation/Slab 11/5/2024 Corrections Issued KIM BEAUCHAMP
Wood Frame 12/2/2024 Corrections Issued KIM BEAUCHAMP
ELECTRICAL-Rough 12/11/2024 Corrections Issued KIM BEAUCHAMP
Gas Test 12/11/2024 Not Ready for Inspection KIM BEAUCHAMP
HVAC-Final 12/11/2024 Not Ready for Inspection KIM BEAUCHAMP
Shower Pan 12/11/2024 Corrections Issued KIM BEAUCHAMP
ELECTRICAL-Final 1/2/2025 Corrections Issued KIM BEAUCHAMP
HVAC-Final 1/2/2025 Approved KIM BEAUCHAMP
PLUMBING-Final 1/2/2025 Approved KIM BEAUCHAMP
Shower Pan 1/2/2025 Approved KIM BEAUCHAMP
ELECTRICAL-Final 1/15/2025 Partial Inspection JOEL GUARDADO
Interior/Exterior Lathing 1/15/2025 Approved JOEL GUARDADO
BUILDING-Rough-Frame 2/4/2025 Approved KIM BEAUCHAMP
Final 2/4/2025 Conditional Approval KIM BEAUCHAMP
Footing/Foundation/Slab 2/4/2025 Approved KIM BEAUCHAMP
Green Building Final 2/4/2025 Approved KIM BEAUCHAMP
Green Building Rough 2/4/2025 Approved KIM BEAUCHAMP
SGSOV-Seismic Gas S/O Valve 2/4/2025 SGSOV Approved KIM BEAUCHAMP
Smoke Detectors 2/4/2025 Approved KIM BEAUCHAMP
Final 2/27/2025 OK to Issue CofO KIM BEAUCHAMP