6108 N SADRING AVE 91367
Certificate Information: 6108 N SADRING AVE 91367
- Application / Permit
- 24014-20000-02217
- Plan Check / Job No.
- B24VN07235
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ENCLOSE THE LOFT WITH ADDITION ON THE 2ND FLOOR . 42 SF OF STOAGE ADDITION ON THE FIRST FLOOR
- Permit Issued
- Issued on 7/11/2024
- Issuing Office
- Current Status
- CofO Issued on 6/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2024 | JOE VO |
| Corrections Issued | 5/25/2024 | JOE VO |
| Quality Review Completed | 6/11/2024 | GARO TELMI |
| Plan Check Approved | 7/1/2024 | JOE VO |
| Issued | 7/11/2024 | APPLICANT |
| CofO in Progress | 4/3/2025 | KIM BEAUCHAMP |
| Permit Finaled | 6/11/2025 | DAVID JAMES |
| CofO Issued | 6/11/2025 | DAVID JAMES |
| Permit Finaled | 6/11/2025 | DAVID JAMES |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/15/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/17/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/17/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: NA93079 | , |
Inspector Information
| JACK UPCHURCH, (818) 374-9853 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/15/2024 | No Access for Inspection | TROY SANDERS |
| Deputy Drilled-In Anchors | 7/30/2024 | Conditional Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2024 | Corrections Issued | JOEL GUARDADO |
| Footing/Foundation/Slab | 11/4/2024 | No Access for Inspection | KIM BEAUCHAMP |
| Wood Frame | 11/4/2024 | No Access for Inspection | KIM BEAUCHAMP |
| Footing/Foundation/Slab | 11/5/2024 | Corrections Issued | KIM BEAUCHAMP |
| Wood Frame | 12/2/2024 | Corrections Issued | KIM BEAUCHAMP |
| ELECTRICAL-Rough | 12/11/2024 | Corrections Issued | KIM BEAUCHAMP |
| Gas Test | 12/11/2024 | Not Ready for Inspection | KIM BEAUCHAMP |
| HVAC-Final | 12/11/2024 | Not Ready for Inspection | KIM BEAUCHAMP |
| Shower Pan | 12/11/2024 | Corrections Issued | KIM BEAUCHAMP |
| ELECTRICAL-Final | 1/2/2025 | Corrections Issued | KIM BEAUCHAMP |
| HVAC-Final | 1/2/2025 | Approved | KIM BEAUCHAMP |
| PLUMBING-Final | 1/2/2025 | Approved | KIM BEAUCHAMP |
| Shower Pan | 1/2/2025 | Approved | KIM BEAUCHAMP |
| ELECTRICAL-Final | 1/15/2025 | Partial Inspection | JOEL GUARDADO |
| Interior/Exterior Lathing | 1/15/2025 | Approved | JOEL GUARDADO |
| BUILDING-Rough-Frame | 2/4/2025 | Approved | KIM BEAUCHAMP |
| Final | 2/4/2025 | Conditional Approval | KIM BEAUCHAMP |
| Footing/Foundation/Slab | 2/4/2025 | Approved | KIM BEAUCHAMP |
| Green Building Final | 2/4/2025 | Approved | KIM BEAUCHAMP |
| Green Building Rough | 2/4/2025 | Approved | KIM BEAUCHAMP |
| SGSOV-Seismic Gas S/O Valve | 2/4/2025 | SGSOV Approved | KIM BEAUCHAMP |
| Smoke Detectors | 2/4/2025 | Approved | KIM BEAUCHAMP |
| Final | 2/27/2025 | OK to Issue CofO | KIM BEAUCHAMP |