20556 W CALIFA ST 91367
Certificate Information: 20556 W CALIFA ST 91367
- Application / Permit
- 24014-20000-02211
- Plan Check / Job No.
- B24VN07209
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 24'-0" x 19'-9.5" ADDITION TO (E) SFD AND 9'-0" x 8'-8" PORCH ADDITION AT FRONT, INTERIOR REMODEL, REMOVE AND REPLACE ALL WINDOWS AND DOORS, AND RE-ROOF.
- Permit Issued
- Issued on 6/20/2024
- Issuing Office
- Current Status
- CofO Issued on 6/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/31/2024 | ISIS ARGUETA |
| Corrections Issued | 6/3/2024 | ISIS ARGUETA |
| Plan Check Approved | 6/19/2024 | SARKIS HARABEDIAN |
| Issued | 6/20/2024 | APPLICANT |
| CofO in Progress | 4/16/2025 | ALEXANDER HANDY |
| Permit Finaled | 6/4/2025 | JOHN JANSON |
| CofO Issued | 6/4/2025 | JOHN JANSON |
| Permit Finaled | 6/4/2025 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2024 | KENIA CASTILLO |
| Roof/Waste drainage to street | Cleared | 6/3/2024 | KENIA CASTILLO |
| Sewer availability | Cleared | 6/3/2024 | KENIA CASTILLO |
| Grading Pre-Inspection | Cleared | 6/19/2024 | ISIS ARGUETA |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Ground Up Builders And Design Inc; Lic. No.: 911849-B | , |
| Contractor | Ground Up Builders; Lic. No.: 911849-B | , |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/28/2024 | Conditional Approval | ALEXANDER HANDY |
| Footing/Foundation/Slab | 6/28/2024 | Corrections Issued | ARUTYUN MADATYAN |
| PLUMBING-Rough | 6/28/2024 | Partial Approval | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 7/1/2024 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 7/1/2024 | Partial Approval | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2024 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 7/29/2024 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2024 | Conditional Approval | ARUTYUN MADATYAN |
| HVAC-Rough | 7/29/2024 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 7/29/2024 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2024 | Approved | GEVORK IPCHYAN |
| Shower Pan | 8/5/2024 | Partial Approval | GEVORK IPCHYAN |
| Insulation | 8/7/2024 | Approved | TROY SANDERS |
| Shower Pan | 8/7/2024 | Approved | TROY SANDERS |
| Drywall Nailing | 8/19/2024 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 8/19/2024 | Partial Approval | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 8/28/2024 | Approved | SCOTT SOBEL |
| Pre-Inspection | 9/5/2024 | Corrections Issued | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 3/24/2025 | Approved | ALEXANDER HANDY |
| Final | 3/24/2025 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 3/24/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Rough | 3/24/2025 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 3/24/2025 | SGSOV Not Ready | ALEXANDER HANDY |
| Smoke Detectors | 3/24/2025 | Approved | ALEXANDER HANDY |
| Final | 4/9/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Green Building Final | 4/9/2025 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 4/9/2025 | SGSOV Approved | JEFFREY HARTLINE |
| Final | 4/15/2025 | OK to Issue CofO | ALEXANDER HANDY |