6958 N NOBLE AVE 91405

Certificate Information: 6958 N NOBLE AVE 91405

Application / Permit
24014-20000-02168
Plan Check / Job No.
B24VN07095
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
DETACHED 21'-6" x 24'-2" TWO-CAR GARAGE CONVERSION TO ACCESSORY DWELLING UNIT WITH (N) 17'-4" X 24'-6" GROUND FLOOR ADDITION PER LAMC 12.22 A.33(c)AND (d).
Permit Issued
Issued on 12/8/2024
Issuing Office
Current Status
CofO in Progress on 5/28/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/21/2024 APPLICANT
Assigned to Plan Check Engineer 5/24/2024 PINANK PATEL
Corrections Issued 5/25/2024 PINANK PATEL
Applicant returned to address corrections 8/8/2024 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 11/1/2024 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 11/6/2024 ALEC MOUSAKHANIAN
Issued 12/8/2024 APPLICANT
CofO in Progress 5/28/2026 VINCENT HANLEY

Permit Application Clearance Information

Address approval Cleared 6/25/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 6/25/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 6/25/2024 BIAINA HARITUNIAN
Sewer availability Cleared 6/25/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 10/29/2024 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 7/24/2025 Approved GAREN HAYRAPETYAN
Underground Mechanical 7/24/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 8/1/2025 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 8/11/2025 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 10/3/2025 Corrections Issued RYAN SALAZAR
Wood Frame 10/3/2025 Not Ready for Inspection RYAN SALAZAR
BUILDING-Rough-Frame 10/7/2025 Not Ready for Inspection RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 10/7/2025 Approved RYAN SALAZAR
Green Building Rough 10/7/2025 Not Ready for Inspection RYAN SALAZAR
Wood Frame 10/7/2025 Not Ready for Inspection RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 10/31/2025 Not Ready for Inspection RYAN SALAZAR
Interior/Exterior Lathing 10/31/2025 Not Ready for Inspection RYAN SALAZAR
BUILDING-Rough-Frame 11/6/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 11/6/2025 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 11/6/2025 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 11/6/2025 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 11/6/2025 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 11/6/2025 Approved MISAEL ESPARZA
Green Building Rough 11/20/2025 Approved JACK KARGODORIAN
Interior/Exterior Lathing 11/20/2025 Partial Approval JACK KARGODORIAN
Rough-Elec/Plmb/HVAC 11/20/2025 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 11/24/2025 Partial Inspection RYAN SALAZAR
Green Building Rough 11/24/2025 Approved RYAN SALAZAR
HVAC-Rough 11/24/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 11/24/2025 Partial Approval RYAN SALAZAR
Insulation 12/3/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 12/3/2025 Partial Approval LOUIS ESCOTO
Shower Pan 12/3/2025 Approved LOUIS ESCOTO
Drywall Nailing 12/9/2025 Not Ready for Inspection RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 12/9/2025 Approved RYAN SALAZAR
HVAC-Rough 12/9/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 12/9/2025 Approved RYAN SALAZAR
Drywall Nailing 12/16/2025 Approved RYAN SALAZAR
Underground Mechanical 12/19/2025 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 3/20/2026 Approved VINCENT HANLEY
ELECTRICAL-Final 3/20/2026 Corrections Issued VINCENT HANLEY
Final 3/20/2026 Corrections Issued VINCENT HANLEY
Green Building Final 3/20/2026 Corrections Issued VINCENT HANLEY
HVAC-Final 3/20/2026 Corrections Issued VINCENT HANLEY
PLUMBING-Final 3/20/2026 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 3/20/2026 SGSOV Not Ready VINCENT HANLEY
Service/Power Release 3/20/2026 Corrections Issued VINCENT HANLEY
Smoke Detectors 3/20/2026 Approved VINCENT HANLEY
ELECTRICAL-Final 3/25/2026 Approved JAVIER RAMOS JR
HVAC-Final 3/25/2026 Corrections Issued JAVIER RAMOS JR
PLUMBING-Final 3/25/2026 Approved JAVIER RAMOS JR
Service/Power Release 3/25/2026 Approved JAVIER RAMOS JR
Final 5/22/2026 Corrections Issued VINCENT HANLEY
Green Building Final 5/22/2026 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/22/2026 SGSOV Approved VINCENT HANLEY
Final 5/28/2026 OK to Issue CofO VINCENT HANLEY